Home TOC Index Previous Next

Operating costs for domestic refrigeration

The Fifteenth Meeting of the Executive Committee agreed to retain the following options for incremental operational cost duration in the domestic refrigeration sector outlined in the paper prepared by the Implementing Agencies so as to enable the Parties concerned to identify the option best suited to their needs.

(a) ten per cent of incremental cost to be paid up-front, or

(b) six months of incremental operating costs calculated at current prices and paid up-front, or incremental operating costs for a duration of one year adjusted according to the prevailing costs at the time of disbursement, when the modified plant was operating, whichever was greater.

(UNEP/OzL.Pro/ExCom/15/45, para. 167).

(Supporting document: UNEP/OzL.Pro/ExCom/15/44).