24th |
23-27 March 1998 |
4 months |
Revise 1998 business plans and work programmes. Complete the remaining projects from the 1997 business plans. Prepare policy papers |
Approve revised 1998 business plans and work programmes. Approve the remaining projects from 1997 business plans. Approve policy papers. Consider funding of projects for process agents |
|
25th |
27-31 July 1998 |
4 months |
Prepare projects, policy papers, progress reports, evaluation of 1997 business plans, national status of phase-out |
Approve projects and policy papers. Review progress reports, evaluation of 1997 business plans and national status of phase-out |
|
26th |
9-13 November 1998* |
4 months |
Prepare projects, policy papers, draft 1999 business plans, necessary elements of work programmes |
Approve projects, policy papers, draft 1999 business plans, necessary and non-contentious elements of work programmes |