Home TOC Index Previous Next


Format for project completion report (non-investment projects)


SECTION 1: PROJECT DATA

1.1 

Country/Region/Global: 

 

1.2 

Project number: (as per inventory) 

 

1.3 

Project title: 

 

1.4 

Date of approval of the project.: 

 

1.5 

Type of Activity: ([ ] Country Programme, [ ] Institutional Strengthening,

[ ] Training, [ ] Networking, [ ] Information exchange, [ ] Workshop). 

1.6 

Implementing agency: 

 

1.7 

Local executing agency/

Financial intermediary: 

 

1.8 

National co-ordinating agency: 

 

1.9 

Scheduled date of completion: 

 

1.10 

Actual date of completion: 

 

1.11 

Date of project completion report: 

 

1.12 

Completion report done by:  

 
 

(Implementing Agency/National Agency) 

 

SECTION 2: EXECUTIVE SUMMARY

Item 

Plan/approved 

Actual 

Comment 

Achievement of project objective (use quantifiable indicators to the extent possible) 

     

Budget and expenditure (US$) 

     

Project implementation (in months) 

     

Project duration 

     

Start-up of project activities at country level as stated by Article 5 Party concerned 

     

Grant agreement submitted to beneficiary 

     

Grant agreement signature 

     

Bids requested 

     

Contracts awarded 

     

Equipment delivered 

     

Principle activity completed (e.g. workshop, training)  

     

Submission of completion report 

     

Overall Assessment of the Project: A brief description of no more than 200 words of the degree the project achieved its objective(s),the manner and the extent the outputs of the projects were being used, major problems encountered and lessons learnt.

SECTION 3: BUDGET AND EXPENDITURES

Information in this section pertain to status reports on project expenditures at the time of preparing the project completion report with the understanding that a full financial completion report will be prepared as a supplement once the accounts of the project are closed.

(A) INSTITUTIONAL STRENGTHENING

3.1 Summary

Item 

Budget (plan)(US $) 

Expenditure (to-date) (US $) 

Difference/Comment (US $) 

Capital costs 

     

Operating cost 

     

Contingency cost 

     

Total 

     

3.2 Budget and Expenditure on Capital Cost

Item* 

Budget 

Expenditure 

Difference 

Reason 

         
         

Total 

       

* List of equipment approved in the project document (additional equipment should be so indicated).

3.3 Budget and Expenditure on Operating Cost

Year 

Item* 

Approved 

Expenditure 

   

Unit cost 

No. of employees** 

Total 

Unit cost 

No. of employees*** 

Total 

 

E.g. Salaries 

           
 

E.g.: Communications 

           
 

Total 

           

* List of incremental operating cost items in the project document

** No. of employees on which the calculation of operating cost is based

*** No. of employees employed at the time of project completion

3.4 Budget and Expenditure on Contingency Cost

 

Item(s) 

Expenditure 

Contingency 

   

Funds 

   
 

Total  

 
 

Approved 

 
 

Difference 

 

(B) TRAINING AND WORKSHOP

3.1 Budget and Expenditure

Item* 

Budget 

Expenditure 

Difference 

Reason 

         

Total 

       

* List all the cost items as approved in the project document

3.2 Budget and Expenditure on Contingency Cost

 

Item(s) 

Expenditure 

Contingency 

   

Funds 

   
 

Total 

 
 

Approved 

 
 

Difference 

 

(C) COUNTRY PROGRAMME, INFORMATION EXCHANGE AND NETWORKING

3.1 Budget and Expenditure

Item* 

Approved 

Expenditure 

Difference 

Reason 

         

Total 

       

* List all the cost items as approved in the project document

SECTION 4: IMPLEMENTATION EFFICIENCY

Item 

Yes 

No 

Delay/comment 

4.1 Project Schedule 

     

Project duration 

     

Start-up of project activities at country level as stated by Article 5 Party concerned 

     

Grant agreement submitted to beneficiary 

     

Grant agreement signature 

     

Bids requested 

     

Contracts awarded 

     

Equipment delivered 

     

Principle activity completed (e.g. workshop, training) 

     

Submission of completion report 

     

4.2 Equipment(where applicable) 

     

Quantity as Planned 

     

Quality as Specified 

     

Delays 

     

4.3 Training 

     

Quantity as Planned 

     

Quality as Specified 

     

Delays 

     

4.4 Please describe any major problems encountered in project implementation and what was the major cause of delay.

SECTION 5: OUTPUTS AND IMPACT

Outputs* 

Achieved as planned 

Impact assessment 

Indicators** 

 

Yes 

No 

Highly satisfactory 

Satisfactory 

Unsatisfactory 

Unacceptable 

 

             

2. 

             

List the outputs one by one as they are described in the project document.

** Indicators should be identified to validate the rating given to the impact assessment of the outputs. The indicators should be chosen to show the extent the outputs have been used by their end-users. For illustration two examples are given in the following table:

Type of Project 

Outputs 

Impact assessment 

Indicators 

Country programme formulation 

A well designed country programme 

Satisfactory 

Frequency of use of the country programme as reference.

Accuracy of the data in the country programme.  

Institutional strengthening 

A well functioning ozone office 

Satisfactory 

Timely and accurate data reported to Ozone Secretariat.

Actions initiated to promote ODS phase-out. 

SECTION 6: OVERALL ASSESSMENT OF PROJECT

Using three indicators, namely achievement of project impact cost and speed of completion (plan v. actual), please give an overall assessment of the project in the scale below.

[ ] Highly satisfactory, more than planned

[ ] Satisfactory, as planned

[ ] Satisfactory, though not as planned

[ ] Unsatisfactory, less than planned

[ ] Unacceptable

Comments from Government:

SECTION 7: LESSONS LEARNT

Please state any lessons that can be drawn from this project that will benefit future projects.

(UNEP/OzL.Pro/ExCom/24/47, Decision 24/9, para. 27).

(Supporting document: UNEP/OzL.Pro/ExCom/24/13).


Home TOC Index Previous Next