1. The
Executive Committee has noted that the Parties decided at their 14th Meeting
(Decision XIV/18
non-compliance with the Montreal Protocol by
(a) "to request that Albania submit to the Implementation Committee a plan of action with time-specific benchmarks to ensure a prompt return to compliance ."; and
(b) " to the degree that Albania is working towards meeting the specific control measures, it should continue to be treated in the same manner as a Party in good standing and should continue to receive international assistance to enable it to return to compliance ".
2. The
Executive Committee has also noted that pursuant to Decision XIV/18,
3. In order to provide immediate assistance to facilitate a return to compliance; and without prejudice to the operations of the Montreal Protocols mechanism dealing with non-compliance, on an exceptional basis, the Executive Committee has entered into an Agreement with the Government of Albania with respect to the complete phase-out of the ozone depleting substances (ODSs) of Annex A Group I, Annex B Group II and Annex E used in Albania.
4.
Table 1: Annual consumption limits for ODSs
in
5. Subject to compliance by Albania with its obligations set out in this Agreement, the Executive Committee agrees in principle to provide a total of US $653,125, excluding agency support costs and funding for institutional strengthening, as the total funding for Albania for the complete phase out of production and consumption of all ODSs, in accordance with the funding disbursement schedule presented in Table 2. The funding for 2003 will be provided at the time of approval of this Agreement; thereafter, the Executive Committee will endeavour to provide the indicated funds at the first meeting of the year.
Table 2: Funding disbursement schedule (US$)
|
Funding |
2003 |
2004 |
2005 |
2006 |
2007 |
2008 |
2009 |
|
118,125 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
181,068 |
172,322 |
72,322 |
42,322 |
22,322 |
22,322 |
22,322 |
|
|
15,356 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
13,580 |
12,924 |
5,424 |
3,174 |
1,674 |
1,674 |
1,674 |
|
|
133,482 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
194,648 |
185,246 |
77,746 |
45,496 |
23,996 |
23,996 |
23,996 |
|
|
Total cost to the MF |
328,130 |
185,246 |
77,746 |
45,496 |
23,996 |
23,996 |
23,996 |
6.
7. The Executive Committee will not provide the funding in accordance with the funding disbursement schedule indicated in Table 2 unless Albania satisfies the following conditions prior to the Executive Committee Meeting where funding is requested for the subsequent implementation programme:
(a) Albania has met the phase-out targets for the applicable year as indicated in Table 1, and these targets have been independently verified as described in paragraph 11;
(b)
(c)
8.
(a) administration matters relating to the National Phase-out Plan;
(b) preparation of annual implementation programmes, based on the regional national phase-out plan to be prepared by the regional inspectors;
(c) co-ordination of all activities and actions identified in the National Phase-out Plan and the monitor of their implementation; and
(d) co-ordination with the National Ozone Unit concerning the preparation and submission of annual reports to the Multilateral Fund Secretariat on the progress of implementation of the National Phase-out Plan and to the Ozone Secretariat on ODS consumption in Albania under Article 7 of the Montreal Protocol.
9. While
the funding was determined on the basis of estimates of the needs of
10.
11. Specifically, UNIDO will be responsible for carrying out the following activities:
(a) ensuring performance and financial verification in accordance with this Agreement and requirements as specified in the National Phase-out Plan;
(b) reporting annually on the implementation of the annual implementation programmes;
(c) providing verification to the Executive Committee that the control targets listed in Table 1 and the associated activities have been met;
(d) ensuring that technical reviews undertaken by UNIDO are carried-out by appropriate independent technical experts;
(e) assisting Albania in the preparation of annual implementation programmes, which will incorporate achievements of previous annual programmes;
(f) carrying-out required supervision missions;
(g) ensuring the presence of an operating mechanism to allow effective, transparent implementation of the programme, and accurate data reporting;
(h) ensuring that disbursements are made to
(i) providing policy development assistance when required.
12. UNEP, as co-operating implementing agency, will be responsible for carrying out the following activities:
(a) assisting
(b) providing reports to UNIDO on these activities, for inclusion in consolidated reports;
(c) ensuring that disbursements are made to
(d) providing policy development assistance when required.
13. The Executive Committee agrees, in principle, to provide UNIDO and UNEP with the agency support costs set out in Table 2.
14.
15. The funding components of this Agreement will not be modified on
the basis of any future Executive Committee decision that may
affect any other related activities in
16.
17. All of the agreements set out in this Agreement are undertaken solely within the context of the Montreal Protocol and do not extend to obligations beyond this Protocol. All terms used in this Agreement have the meaning ascribed to them in the Protocol unless otherwise defined herein.
(UNEP/OzL.Pro/ExCom/39/43, Decision 39/43, para. 81).
(Supporting document: UNEP/OzL.Pro/ExCom/39/43, Annex X).