1. The Executive
Committee approves in principle a total of US $9 million in funding for
the phased reduction and complete phase-out of consumption
of CFC-11, CFC-12 and CFC-115 in
2. By this agreement,
Table 1. National control targets for CFC-11, CFC-12 and CFC-115 consumption in ODP tonnes
|
|
1999 Baseline |
2001 |
2002 |
2003 |
2004 |
2005 |
2006 |
2007 |
2008 |
2009 |
|
736 |
700 |
650 |
334 |
166 |
100 |
0 |
0 |
0 |
0 |
|
|
1,049 |
300 |
250 |
200 |
150 |
50 |
0 |
0 |
0 |
0 |
|
|
9 |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
|
|
977 |
909 |
534 |
316 |
150 |
0 |
0 |
0 |
0 |
|
|
Total agreed funding (US$ million) |
|
3.5 |
2.5 |
1 |
0.75 |
0.75 |
0.5 |
0 |
0 |
0 |
|
Agency support cost (US$ million) |
|
0.295 |
0.175 |
0.150 |
0.045 |
0.03 |
0.03 |
0.03 |
0.03 |
0.025 |
3. The Executive Committee also agrees in principle that the funds will be provided at the last meeting of the Executive Committee in a given year, for the exact amount listed in the above table for that year and on the basis of an annual implementation plan for the following year, subject to the performance requirements contained in this agreement. Thus, for example, the payment indicated in year 2001 will be for activities to be undertaken in 2002, and so on.
4. Payments noted in
Table 1, other than those for 2001, will be released based on confirmation
that: the agreed phase-out targets noted in Table 1 for the
previous year have been achieved; it has been verified that the activities
planned for the previous year were undertaken in accordance with the annual
implementation plan, and CFC phase-out contracts have been signed amounting to
at least 80 per cent of the Multilateral
Fund funding approved for the relevant annual programme. For example, payment
in 2002 for the implementation of the 2003 work programme will be conditional on satisfactory verification that
5. The Government
of
6. The Government of Turkey also agrees to allow independent verification audits as provided for in this agreement, and in addition, external evaluation as may be directed by the Executive Committee, to verify that annual CFC consumption levels correspond to those agreed in Table 1 and that implementation of the sector plan proceeds as scheduled and agreed in annual implementation programmes.
7. The Turkish
refrigeration plan which supports this Agreement,
Turkish Country Programme and other related documentation may include estimates
of specific funds that were thought to be needed for specific items.
Notwithstanding this, the Executive Committee wishes to provide
8. The Government of Turkey agrees that the funds being agreed in principle by the Executive Committee at its 35th Meeting for the complete phase-out of CFC-11, CFC-12 and CFC-115 consumption are the total funding that will be available to Turkey to allow its full compliance with the reduction and phase-out as agreed with the Executive Committee of the Multilateral Fund, and that no additional Multilateral Fund resources will be forthcoming for any related activities in the refrigeration sector. It is also understood that aside from the agency fee referred to in paragraph 10 below, the Government of Turkey, the Multilateral Fund, and its Implementing Agencies, and bilateral donors will neither request nor provide further Multilateral Fund-related funding for the accomplishment of the total phase-out of CFCs in the refrigeration sector.
9. The Government of Turkey agrees that if the Executive Committee meets its obligations under this Agreement, but Turkey does not meet the reduction requirements outlined in paragraph 2, or other requirements outlined in this document, the implementing agency and the Multilateral Fund will withhold funding for subsequent tranches of funding outlined in paragraph 2 until such time as the required reduction has been met. It is clearly understood that the fulfilment of this agreement depends on satisfactory performance by both the Government of Turkey and the Executive Committee of their obligations. In addition, Turkey understands that with respect to all calendar year targets beginning with 2002, as set out in paragraph 2 of this agreement, the Multilateral Fund will reduce the subsequent tranche and therefore the total funding for CFC-11, CFC-12 and CFC-115 phase-out on the basis of US $15,000 per ODP tonne of reduction not achieved in any year.
10. The World Bank has agreed to be the implementing agency for the implementation of this sector plan which will be completed in 2006. It is also agreed that monitoring will continue until 2009 in order to ensure compliance during the period 2006 to 2009. A fee of 9 per cent of the sector plan annual funding has been agreed in accordance with the provisions of this Agreement, and distributed as shown in Table 1. As the implementing agency, the World Bank will be responsible for the following:
(a) ensuring performance and financial verification in accordance with specific World Bank procedures and requirements as specified in the Turkish refrigeration sector plan, as revised;
(b) reporting on the implementation of the annual implementation programmes to be included as part of each annual programme starting with the submission for the 2003 annual implementation programme prepared in 2002;
(c) providing verification to the Executive Committee that the control targets listed in Table 1 and the associated activities have been met;
(d) ensuring that technical reviews undertaken by the World Bank are carried out by appropriate independent technical experts;
(e) assisting
(f) carrying out required supervision missions;
(g) ensuring the presence of an operating mechanism to allow effective, transparent implementation of the programme, and accurate data reporting;
(h) verification for the Executive Committee that CFC consumption for the refrigeration sector has been completed based on the schedules listed in Table 1;
(i) ensuring
that disbursements are made to
(j) providing policy development assistance when required.
9. The funding components of this Decision shall not be modified on the basis of future Executive Committee decisions that may affect the funding of any other consumption sector projects or any other related activities in the country.
(UNEP/OzL.Pro/ExCom/35/67, Decision 35/55, para. 91).
(Supporting document: UNEP/OzL.Pro/ExCom/35/54, 35/54/Corr.1 and 35/54/Add.1).
UNEP/OzL.Pro/2/3 Report of the Second Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/2/3, Annex IV, Appendix I Indicative List of Categories of Incremental Costs
UNEP/OzL.Pro/4/15,
Annex VIII Date:
UNEP/OzL.Pro/2/3, Annex IV, Appendix II Terms of Reference of the Executive Committee
UNEP/OzL.Pro/4/15,
Annex X Date:
UNEP/OzL.Pro/2/3, Annex IV, Appendix IV Terms of Reference for the Interim Multilateral Fund
Date:
UNEP/OzL.Pro/3/11 Report of the Third Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/3/11, Annex VI Rules of Procedure for Meeting of the Executive Committee
UNEP/OzL.Pro/ExCom/3/18/Rev.1, Annex II of the Interim Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/4/15 Report of the Fourth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/4/15, Annex VI Approved Destruction Technologies
Date:
UNEP/OzL.Pro/4/15, Annex VII Suggested Regulatory Standards for Destruction Facilities
Date:
UNEP/OzL.Pro/4/15, Annex IX Terms of Reference for the Multilateral Fund
Date:
UNEP/OzL.Pro/5/12 Report of the Fifth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/6/7 Report of the Sixth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/7/12 Report of the Seventh Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/8/12 Report of the Eighth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/7/12, Annex IV Categories and Examples of Laboratory Uses
Date:
UNEP/OzL.Pro/7/12, Annex V Actions to Improve the Financial Mechanism for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/9/12 Report of the Ninth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/9/12, Annex X Arrears to the Multilateral Fund from Countries that Had Not Ratified the London Amendment
Date:
UNEP/OzL.Pro/10/9 Report of the Tenth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/11/10 Report of the Eleventh Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/12/9 Report of the Twelfth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/13/10 Report of the Thirteenth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/14/9 Report of the Fourteenth Meeting of the Parties to the Montreal Protocol on Substances that Deplete the Ozone Layer
Date:
UNEP/OzL.Pro/ExCom/1/2 Report of the First Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/2/5/Rev.1 Report of the Second Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/2/5/Rev.1, Annex I Procedural Arrangements among the International Bank for Reconstruction and Development (World Bank), the United Nations Environment Programme (UNEP and the United Nations Development Programme (UNDP)
Date:
UNEP/OzL.Pro/ExCom/3/18/Rev.1 Report of the Third Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/3/18/Rev.1, Annex III Implementation Guidelines and Criteria for Project Selection
Date:
UNEP/OzL.Pro/ExCom/4/13/Rev.1 Report of the Fourth Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/5/4/Rev.2 Agreement between the United Nations Environment Programme as the Treasurer of the Interim Multilateral Fund for the Montreal Protocol and the Executive Committee of the Interim Multilateral Fund established by the Parties to the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/5/16 Report of the Fifth Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/5/16, Annex III Procedures for Presentation of Country Programmes and Project Proposals to the Executive Committee
Date:
UNEP/OzL.Pro/ExCom/5/16, Annex IV Bilateral and Regional Co-operation
Date:
UNEP/OzL.Pro/ExCom/5/Inf.2 Agreement between the Executive Committee of the Interim Multilateral Fund for the Implementation of the Montreal Protocol and the International Bank for Reconstruction and Development (World Bank)
Date:
UNEP/OzL.Pro/ExCom/5/Inf.3 Agreement between the Executive Committee of the Interim Multilateral Fund for the Implementation of the Montreal Protocol and the United Nations Development Programme
Date:
UNEP/OzL.Pro/ExCom/5/Inf.4 Agreement between the Executive Committee of the Interim Multilateral Fund for the Implementation of the Montreal Protocol and the United Nations Environment Programme
Date:
UNEP/OzL.Pro/ExCom/7/20 Institutional Strengthening
Date: 26 May 1992
UNEP/OzL.Pro/ExCom/7/21 and Rev.1 Further Definition of Incremental Costs
Date: 28 May 1992
UNEP/OzL.Pro/ExCom/7/28 Establishment of a Financial Mechanism under Article 10 of the Amended Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/7/30 Report of the Seventh Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/7/30, Annex III Guidelines for Presentation of Projects and Criteria for Project Approval
Date:
UNEP/OzL.Pro/ExCom/7/30, Annex IV Guidelines for Cost Assessment of Bilateral and Regional Activities
Date:
UNEP/OzL.Pro/ExCom/7/30, Annex V Whether Support from the Fund Could Be Given Retroactively
Date:
UNEP/OzL.Pro/ExCom/7/30, Annex VI Should the Fund Finance Activities Related to Enterprises that Are Wholly or Partly Owned by Transnational Corporations
Date:
UNEP/OzL.Pro/ExCom/7/30, Annex VII Whether the Fund Should Finance Activities Related to Enterprises that Are Wholly or Partly Owned by Countries that Are Not Parties to the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/7/Inf.3 Rationale for Funding Institutional Strengthening from the Interim Multilateral Fund of the Montreal Protocol (submitted by the World Bank)
Date: 27 May 1992
UNEP/OzL.Pro/ExCom/7/Inf.4 Operational Interpretations of Incremental Costs and Eligible Expenditures for the Interim Multilateral Fund of the Montreal Protocol (submitted by the World Bank)
Date: 28 May 1992
UNEP/OzL.Pro/ExCom/8/25, and Add.1 Meeting of the Needs of Article 5 Parties for Controlled Substances during the Grace and Phase Out Periods
Date:
UNEP/OzL.Pro/ExCom/8/29 Report of the Eighth Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/8/29, Annex III Sub-Committee Recommendations
Date:
UNEP/OzL.Pro/ExCom/8/29, Annex IV Agreement between the Executive Committee of the Interim Multilateral Fund for the Implementation of the Montreal Protocol and the United Nations Industrial Development Organisation
Date:
UNEP/OzL.Pro/ExCom/9/20 Report of the Ninth Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/9/20, Annex II Sub-Committee on Financial Matters
Date:
UNEP/OzL.Pro/ExCom/10/39 Incremental Cost Policies and Operational Interpretation
Date: 28 May 1993
UNEP/OzL.Pro/ExCom/10/40 Report of the Tenth Meeting of the Executive Committee of the Multilateral Fund under the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/10/40, Annex II Proposed Three-Year Plan and Budget of the Multilateral Fund (1994-1996)
Date:
UNEP/OzL.Pro/ExCom/11/36 Report of the Eleventh Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/12/4 Promissory Notes: Report from the Treasurer
Date:
UNEP/OzL.Pro/ExCom/12/6 Uniform Format for Future Financial Reports
Date:
UNEP/OzL.Pro/ExCom/12/30 Review of Project Proposals
Date:
UNEP/OzL.Pro/ExCom/12/32 The Use of Contingency Costs in Project Proposals
Date:
UNEP/OzL.Pro/ExCom/12/33 Report on Strategic Options for Retrofitting of Mobile Air Conditioners and Chillers
Date:
UNEP/OzL.Pro/ExCom/12/34 The Use of Transitional Substances as Substitutes for Ozone Depleting Substances
Date:
UNEP/OzL.Pro/ExCom/12/35 Draft Terms of Reference for the Review under Paragraph 8 of Article 5 of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/12/37 Report of the Twelfth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/12/37, Annex II Encashment Schedule for Promissory Notes
Date:
UNEP/OzL.Pro/ExCom/12/37, Annex III Uniform Format for Annual Financial Reports from Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/12/37, Annex IV Recommended Guidelines for Project Reviews
Date:
UNEP/OzL.Pro/ExCom/12/37, Annex V Terms of Reference for the Review under Paragraph 8 of Article 5 of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/13/42 Projects that Might Realise Net Incremental Savings
Date:
UNEP/OzL.Pro/ExCom/13/46, Format for the Presentation of Information on Progress of Implementation of Country Programmes
Date:
UNEP/OzL.Pro/ExCom/13/47 Report of the Thirteenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/13/47, Annex II Information on Progress of Implementation of Country Programmes
Date:
UNEP/OzL.Pro/ExCom/14/15 Report of the Fourteenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/14/15, Annex II Report of the Sub-Committee for the Report on the Review under Paragraph 8 of Article 5 of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/15/44 Options for Incremental Operational Cost Duration in the Domestic Refrigeration Sector (submitted by UNDP, UNIDO and the World Bank)
Date:
UNEP/OzL.Pro/ExCom/15/45 Report of the Fifteenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/15/45, Annex III Terms of Reference for an Expert Group on the Production of Substitutes for Ozone Depleting Substances
Date:
UNEP/OzL.Pro/ExCom/16/13 Report of the Ad Hoc Working Group on Project Preparation and Evaluation
Date:
UNEP/OzL.Pro/ExCom/16/16 Incremental Operating Costs and Savings in the Halon Portable Fire Extinguisher Sub-Sector
Date:
UNEP/OzL.Pro/ExCom/16/17 Methodology for Calculation of Incremental Operational Costs in Methylene Chloride Projects
Date:
UNEP/OzL.Pro/ExCom/16/19 Procedural Modification to Assist Policy Communications
Date:
UNEP/OzL.Pro/ExCom/16/20 Report of the Sixteenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/16/20, Annex II Actions on Project Preparation and Evaluation
Date:
UNEP/OzL.Pro/ExCom/16/20, Annex III Procedural Modification to Assist Policy Communications
Date:
UNEP/OzL.Pro/ExCom/16/20, Annex IV Methodology for Calculation of Incremental Operational Costs in Methylene Chloride Projects
Date:
UNEP/OzL.Pro/ExCom/17/60 Report of the Seventeenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/17/60, Annex II Uniform Format for Reporting Progress and Financial Information
Date:
UNEP/OzL.Pro/ExCom/18/68 Strategy Paper for Low-halon Consuming Countries
Date:
UNEP/OzL.Pro/ExCom/18/69 Guidelines for Halon Banking
Date:
UNEP/OzL.Pro/ExCom/18/73 Technology Upgrades
Date:
UNEP/OzL.Pro/ExCom/18/75 Report of the Eighteenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/18/75, Annex II Multilateral Fund Secretariat Revised Budget for 1996 and Proposed Budgets for 1997 and 1998
Date:
UNEP/OzL.Pro/ExCom/18/75, Annex V Recommendations on Projects
Date:
UNEP/OzL.Pro/ExCom/19/4 Revised format for financial and progress reporting
Date:
UNEP/OzL.Pro/ExCom/19/51 Progress of implementation of country programmes
Date:
UNEP/OzL.Pro/ExCom/19/52, Corr.1 Guidelines for renewal of institutional strengthening projects
Date:
UNEP/OzL.Pro/ExCom/19/53 Approaches to the phase-out of ODS in low-ODS-consuming countries
Date:
UNEP/OzL.Pro/ExCom/19/54 Approaches to ODS phase-out in small- and medium-sized enterprises
Date:
UNEP/OzL.Pro/ExCom/19/55, Corr.1 The role of cost-effectiveness thresholds in sectoral phase-out proposals and guidelines for umbrella projects
Date:
UNEP/OzL.Pro/ExCom/19/57 Duration of transitional periods for incremental operating costs and savings
Date:
UNEP/OzL.Pro/ExCom/19/58 Three-year rolling business plan
Date:
UNEP/OzL.Pro/ExCom/19/59 Report of the second meeting of the Expert Group on the production of substitutes for ozone-depleting substances
Date:
UNEP/OzL.Pro/ExCom/19/60 Terms of reference for the study on technology transfer
Date:
UNEP/OzL.Pro/ExCom/19/61 Change of ownership of approved projects
Date:
UNEP/OzL.Pro/ExCom/19/62 Training strategy
Date:
UNEP/OzL.Pro/ExCom/19/64 Report of the Nineteenth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date: 10 May 1996
UNEP/OzL.Pro/ExCom/19/64, Annex V Revisions to Data Base Format for Progress and Financial Reporting
Date: 10 May 1996
UNEP/OzL.Pro/ExCom/19/64, Annex VI Preliminary Data on the Production Sector
Date: 10 May 1996
UNEP/OzL.Pro/ExCom/19/64, Annex VII Form for the Sector Phase-Out Plan
Date: 10 May 1996
UNEP/OzL.Pro/ExCom/19/64, Annex VIII Terms of Reference for the Technical Audit
Date: 10 May 1996
UNEP/OzL.Pro/ExCom/20/40, Corr.1 Consolidated progress report
Date:
UNEP/OzL.Pro/ExCom/20/56, Rev.1 Progress of implementation of country programmes
Date:
UNEP/OzL.Pro/ExCom/20/57 Discrepancy between the data reported by a Party to the Ozone Secretariat and the data presented by the Party to the Executive Committee of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/20/58 Monitoring and Evaluation System for the Multilateral Fund (a draft report)
Date:
UNEP/OzL.Pro/ExCom/20/59 Concessional lending for ODS phase-out
Date:
UNEP/OzL.Pro/ExCom/20/60 Report on UNEP’s continued work on addressing the needs of low volume ODS consuming countries (LVCs)
Date:
UNEP/OzL.Pro/ExCom/20/61 Phase-out of ozone-depleting substances in small- and medium-sized enterprises (a paper from the Fund Secretariat)
Date:
UNEP/OzL.Pro/ExCom/20/62, Corr.1 Residual sectoral consumption and umbrella projects
Date:
UNEP/OzL.Pro/ExCom/20/63 Report on the first meeting of the Executive Committee’s Subgroup on the Production Sector
Date:
UNEP/OzL.Pro/ExCom/20/64 Guidelines for calculating incremental costs in the tobacco sector
Date:
UNEP/OzL.Pro/ExCom/20/65 Safety related costs in projects using hydrocarbon technology
Date:
UNEP/OzL.Pro/ExCom/20/66 Capital and operating costs in the halon fire extinguisher sub-sector
Date:
UNEP/OzL.Pro/ExCom/20/67 Study on low pressure versus high pressure foaming machines
Date:
UNEP/OzL.Pro/ExCom/20/68,
Rev.1 Report on implementation of the
Date:
UNEP/OzL.Pro/ExCom/20/69 The application of hydrochlorofluorocarbons (HCFCs) in projects funded by the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/20/70 Report on the work currently in progress on alternatives to methyl bromide
Date:
UNEP/OzL.Pro/ExCom/20/71 Study on technology transfer
Date:
UNEP/OzL.Pro/ExCom/20/72 Report of the Twentieth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/20/72, Annex VI Interim Guidelines on Methyl Bromide Projects
Date:
UNEP/OzL.Pro/ExCom/21/4 Administrative costs of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/21/5 Financial planning and projections of cash flow for the triennium 1997-1999
Date:
UNEP/OzL.Pro/ExCom/21/6 Three-year (1997-1999) business plan of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/21/7 Overview of the 1997 business plans of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/21/8 1997 UNDP business plan
Date:
UNEP/OzL.Pro/ExCom/21/9 1997 UNEP business plan
Date:
UNEP/OzL.Pro/ExCom/21/10 1997 UNIDO business plan
Date:
UNEP/OzL.Pro/ExCom/21/11 1997 World Bank business plan
Date:
UNEP/OzL.Pro/ExCom/21/12 Report of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/21/24
Date:
UNEP/OzL.Pro/ExCom/21/29 Report of the Executive Committee’s Sub-Group on the Production Sector
Date:
UNEP/OzL.Pro/ExCom/21/30 Monitoring and evaluation system for the Multilateral Fund (revised draft from the consultant)
Date:
UNEP/OzL.Pro/ExCom/21/31 Retroactive funding
Date:
UNEP/OzL.Pro/ExCom/21/32 Technology transfer
Date:
UNEP/OzL.Pro/ExCom/21/33 Report on actions to improve the functioning of the Financial Mechanism, Decision VIII/5)
Date:
UNEP/OzL.Pro/ExCom/21/34 Concessional lending
Date:
UNEP/OzL.Pro/ExCom/21/35 Discussion paper for the establishment of training guidelines for identification of needs and co-ordination of activities (submitted by UNEP IE)
Date:
UNEP/OzL.Pro/ExCom/21/36 Report of the Twenty-first Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/21/36, Annex VI Initial Guidance to Allow Further Development by China and the World Bank of the Halon Sector Approach Pilot Programme Under and Umbrella Agreement
Date:
UNEP/OzL.Pro/ExCom/21/36, Annex VII Terms of Reference of the Monitoring, Evaluation, and Finance Sub-Committee
Date:
UNEP/OzL.Pro/ExCom/22/5 Report of the Sub-Committee on Monitoring, Evaluation and Finance
Date: 29 May 1997
UNEP/OzL.Pro/ExCom/22/6 Evaluation of 1996 business plans of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/22/7 Consolidated revised 1997 business plans of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/22/8 UNDP revised 1997 business plan
Date:
UNEP/OzL.Pro/ExCom/22/9 UNEP revised 1997 business plan
Date:
UNEP/OzL.Pro/ExCom/22/10 UNIDO revised 1997 business plan
Date:
UNEP/OzL.Pro/ExCom/22/11 World Bank revised 1997 business plan
Date:
UNEP/OzL.Pro/ExCom/22/12 Three year (1997-1999) business plan of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/22/13 Summary status report on ODS phase-out for Article 5 countries
Date:
UNEP/OzL.Pro/ExCom/22/14 Indicators for the evaluation of the performance of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/22/15 Report of the Sub-Committee on Project Review
Date: 28 May 1997
UNEP/OzL.Pro/ExCom/22/16 Overview of issues identified during project review
Date: 4 May 1997
UNEP/OzL.Pro/ExCom/22/68 Report of the Executive Committee’s Subgroup on the Production Sector
Date: 27 May 1997
UNEP/OzL.Pro/ExCom/22/69 Report on options to advance phase-out in the SME sector
Date:
UNEP/OzL.Pro/ExCom/22/70 Progress of implementation of country programmes: Implications of using different baseline years
Date:
UNEP/OzL.Pro/ExCom/22/71 Discrepancy between data reported to the Ozone and Fund Secretariats: Reconciliation and harmonisation of the two parallel streams of data reporting
Date: 1 May 1997
UNEP/OzL.Pro/ExCom/22/72 Draft guidelines for proposals to change technology in approved projects
Date:
UNEP/OzL.Pro/ExCom/22/73 Incremental operating costs for domestic refrigeration compressors
Date:
UNEP/OzL.Pro/ExCom/22/74 Training guidelines for identification of needs and co-ordination of activities
Date: 3 May 1997
UNEP/OzL.Pro/ExCom/22/76 Actions to improve the functioning of the Financial Mechanism (Decision VIII/5)
Date:
UNEP/OzL.Pro/ExCom/22/77 Sector plan for phase-out
in
Date:
UNEP/OzL.Pro/ExCom/22/79/Rev.1 Report of the Twenty-second Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/22/79/Rev.1, Annex III Work programme and work plan on monitoring and evaluation of the Multilateral Fund for a twelve-month period between 1997-1998
Date:
UNEP/OzL.Pro/ExCom/22/79/Rev.1, Annex VII Progress of implementation of country programmes
Date:
UNEP/OzL.Pro/ExCom/23/4 Report of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/23/4/Add.1 Report of the Third Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/23/5 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/23/6 Standard components on monitoring and evaluation in project proposals
Date:
UNEP/OzL.Pro/ExCom/23/7 Format of project completion reports
Date:
UNEP/OzL.Pro/ExCom/23/10 and Add.1 Reports of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/23/11
Date:
UNEP/OzL.Pro/ExCom/23/17/Rev.1 and Add.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/23/52 Guidelines for the preparation of Refrigerant Management Plan (RMP)
Date:
UNEP/OzL.Pro/ExCom/23/53 Baseline equipment
Date:
UNEP/OzL.Pro/ExCom/23/54 Safety related costs of hydrocarbon technologies
Date:
UNEP/OzL.Pro/ExCom/23/55 Draft guidelines for cost-effectiveness thresholds in the tobacco sector
Date:
UNEP/OzL.Pro/ExCom/23/61 Issues remaining from Twenty-second Meeting
Date:
UNEP/OzL.Pro/ExCom/23/62 Report of the Executive Committee’s Subgroup on the Production Sector
Date:
UNEP/OzL.Pro/ExCom/23/63 Criteria for project preparation
Date:
UNEP/OzL.Pro/ExCom/23/64 Prices of chemicals
Date:
UNEP/OzL.Pro/ExCom/23/66 Draft guideline for liquid carbon dioxide technology in foam projects
Date:
UNEP/OzL.Pro/ExCom/23/Inf.3 Guidelines for Liquid Carbon Dioxide projects (Submitted by UNDP)
Date:
UNEP/OzL.Pro/ExCom/23/Inf.4 Training Guidelines for Identification of Needs and Co-ordination of Activities (Submitted by UNEP IE)
Date:
UNEP/OzL.Pro/ExCom/23/68 Report of the Twenty-third Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/23/68, Annex II Evaluation Guide
Date:
UNEP/OzL.Pro/ExCom/23/68, Annex III Format for project completion reports (investment projects)
Date:
UNEP/OzL.Pro/ExCom/24/4 Report of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/24/11 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/24/12 Non-investment project milestones
Date:
UNEP/OzL.Pro/ExCom/24/13 Format for project completion report (non-investment project) (Revised Draft)
Date:
UNEP/OzL.Pro/ExCom/24/14 Status of preparation of investment project completion reports
Date:
UNEP/OzL.Pro/ExCom/24/15 Co-financing
Date:
UNEP/OzL.Pro/ExCom/24/16 Status of recruitment of Monitoring and Evaluation Officer
Date:
UNEP/OzL.Pro/ExCom/24/17 Report of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/24/18 Strategy and guidelines for investment projects in the methyl bromide sector
Date:
UNEP/OzL/Pro/ExCom/24/19 and Corr.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/24/38 and Corr.1 Safety related costs of hydrocarbon technology
Date:
UNEP/OzL.Pro/ExCom/24/39 Draft guidelines for liquid carbon dioxide technology in foam projects
Date:
UNEP/OzL.Pro/ExCom/24/43 Report of the Executive Committee’s Subgroup on the Production Sector
Date:
UNEP/OzL.Pro/ExCom/24/44 Analysis of use of HCFC technologies in Fund-assisted projects
Date:
UNEP/OzL.Pro/ExCom/24/47 Report of the Twenty-fourth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/24/47, Annex II Non-investment project milestones
Date:
UNEP/OzL.Pro/ExCom/24/47, Annex III Format for project completion report (non-investment projects)
Date:
UNEP/OzL.Pro/ExCom/24/47, Annex IV Strategy and guidelines for projects in the methyl bromide sector
Date:
UNEP/OzL.Pro/ExCom/24/47, Annex VI Guidelines for liquid carbon dioxide projects
Date:
UNEP/OzL.Pro/ExCom/25/4 Report of the Fifth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/25/6 and Corr.1 Promissory notes
Date:
UNEP/OzL.Pro/ExCom/25/7 Project implementation delays: Bankruptcy
Date:
UNEP/OzL.Pro/ExCom/25/8 Evaluation of 1997 business plans
Date:
UNEP/OzL.Pro/ExCom/25/9 Consolidated progress report
Date:
UNEP/OzL.Pro/ExCom/25/15 Consolidated project completion report
Date:
UNEP/OzL.Pro/ExCom/25/16 and Rev.1 Summary status report on ODS phase-out in Article 5 countries
Date:
UNEP/OzL.Pro/ExCom/25/17 Report of the Fourteenth Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/25/18 and Corr.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/25/54 Hydrocarbon safety
Date:
UNEP/OzL.Pro/ExCom/25/55 Baseline equipment
Date:
UNEP/OzL.Pro/ExCom/25/56 Incremental operating costs for compressors
Date:
UNEP/OzL.Pro/ExCom/25/57 Terminal umbrella projects
Date:
UNEP/OzL.Pro/ExCom/25/58 and Corr.1 Retrofit of commercial refrigeration equipment
Date:
UNEP/OzL.Pro/ExCom/25/65 Concessional lending
Date:
UNEP/OzL.Pro/ExCom/25/66 and Add.1 Administrative costs of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/25/67 Report of the production sector subgroup
Date:
UNEP/OzL.Pro/ExCom/25/Inf.2 Host government agreement
Date:
UNEP/OzL.Pro/ExCom/25/68 Report of the Twenty-fifth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/25/68, Annex II Amendments to the Agreement
between the Executive Committee of the (then Interim) Multilateral
Fund for the Implementation of the Montreal Protocol
and the United Nations Development Programme, signed on
Date:
UNEP/OzL.Pro/ExCom/26/4 Report of the Sixth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/26/5 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/26/6 Performance indicators for the evaluation of business plans
Date:
UNEP/OzL.Pro/ExCom/26/7 Summary table on the status of ODS phase-out in Article 5 countries
Date:
UNEP/OzL.Pro/ExCom/26/13 Status of implementation of the monitoring and evaluation work programme
Date:
UNEP/OzL.Pro/ExCom/26/15 Proposed Budget of the Fund Secretariat for 1999
Date:
UNEP/OzL.Pro/ExCom/26/16 Report of the Fifteenth Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/26/17 and Cor.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/26/58 Incremental operating costs for compressors
Date:
UNEP/OzL.Pro/ExCom/26/59 Baseline equipment
Date:
UNEP/OzL.Pro/ExCom/26/60 Retrofit of commercial refrigeration equipment
Date:
UNEP/OzL.Pro/ExCom/26/66 Report of the Executive Committee’s Subgroup on Production Sector
Date:
UNEP/OzL.Pro/ExCom/26/67 Administrative costs of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/26/70 Report of the Twenty-sixth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/27/4 Report of the Seventh Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/27/5 and Corr.1 Consolidated 1999 business plan of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/27/6 1999 business plans for bilateral co-operation
Date:
UNEP/OzL.Pro/ExCom/27/7 and Corr.1 1999 business plans of UNDP
Date:
UNEP/OzL.Pro/ExCom/27/8 and Corr.1 1999 business plans of UNEP
Date:
UNEP/OzL.Pro/ExCom/27/9 and Corr.1 1999 business plans of UNIDO
Date:
UNEP/OzL.Pro/ExCom/27/10 1999 business plans of World Bank
Date:
UNEP/OzL.Pro/ExCom/27/11 and Corr.1 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/27/12 Draft monitoring and evaluation work programme for 1999
Date:
UNEP/OzL.Pro/ExCom/27/13 Report of the Sixteenth Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/27/14 and Corr.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/27/37 Possible consideration of a new sub-sector for transportation refrigeration
Date:
UNEP/OzL.Pro/ExCom/27/38 Eligibility of ODS consumption arising from evaporation losses in the foam industry
Date:
UNEP/OzL.Pro/ExCom/27/39 Circumstances for the consideration of ODS phase out in the commercial refrigeration end-user sector
Date:
UNEP/OzL.Pro/ExCom/27/40 Process agents: implementation of Decision X/14 (paragraphs 3, 5, and 6) of the Tenth Meeting of the Parties
Date:
UNEP/OzL.Pro/ExCom/27/41 Phase-out plan for the solvent
sector in
Date:
UNEP/OzL.Pro/ExCom/27/45, Corr.1, Add.1 Production sector
Date:
UNEP/OzL.Pro/ExCom/27/46 Export to non-Article 5 countries: guidelines for project eligibility
Date:
UNEP/OzL.Pro/ExCom/27/47 Concessional loans
Date:
UNEP/OzL.Pro/ExCom/27/48, Corr.1, Corr.2 Report of the Twenty-seventh Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/27/48, Annex III Framework Guidelines/Broad Principles for Process Agent Projects
Date:
UNEP/OzL.Pro/ExCom/27/48, Annex IV Agreement for the China Production Sector
Date:
UNEP/OzL.Pro/ExCom/28/4 Report of the Eighth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/28/5 Consolidated progress report
Date:
UNEP/OzL.Pro/ExCom/28/11 Consequences of project cancellations
Date:
UNEP/OzL.Pro/ExCom/28/12 Evaluation of 1998 business plans
Date:
UNEP/OzL.Pro/ExCom/28/13 Shares of the Implementing Agencies
Date:
UNEP/OzL.Pro/ExCom/28/14 Summary status report on ODS phase-out in Article 5 countries (1999 update)
Date:
UNEP/OzL.Pro/ExCom/28/16 Interim report on the implementation of the 1999 work programme for monitoring and evaluation
Date:
UNEP/OzL.Pro/ExCom/28/18 Report of the Seventeenth Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/28/19/Rev.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/28/47 Circumstances for the consideration of ODS phase-out in the commercial refrigeration end-user sector: additional considerations
Date:
UNEP/OzL.Pro/ExCom/28/48 The sterilants sector
Date:
UNEP/OzL.Pro/ExCom/28/49 Strategy plan of ODS
phase-out from production of extruded
polyethylene and polystyrene foams sub sectors of
Date:
UNEP/OzL.Pro/ExCom/28/50 and Corr.1
Date:
UNEP/OzL.Pro/ExCom/28/52 and Corr.1 Revision of the guidelines for the methyl bromide sector
Date:
UNEP/OzL.Pro/ExCom/28/53 Report on concessional lending (a discussion paper by the Secretariat)
Date:
UNEP/OzL.Pro/ExCom/28/54 and Add.1 Report on implementation of the new administrative cost regime
Date:
UNEP/OzL.Pro/ExCom/28/55 Export to non-article 5 countries: Report on project eligibility
Date:
UNEP/OzL.Pro/ExCom/28/Inf.2 Production of domestic refrigerators, freezers and hermetic compressors (submitted by the Government of China as per Decision 27/16)
Date:
UNEP/OzL.Pro/ExCom/28/Inf.3 Discussion paper submitted by the Government of Sweden on policy on HCFCs
Date:
UNEP/OzL.Pro/ExCom/28/Inf.4 Concessional lending under the Multilateral Fund (a discussion paper from the Swedish Delegation)
Date:
UNEP/OzL.Pro/ExCom/28/Inf.5 Conclusions of the meeting of the informal group on technology transfer
Date:
UNEP/OzL.Pro/ExCom/28/57 Report of the Twenty-eighth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/29/4 Report of the Ninth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/29/5, Add.1, Corr.1 Report on the implementation of the 1999 work programme for monitoring and evaluation
Date:
UNEP/OzL.Pro/ExCom/29/6 Draft work programme for monitoring and evaluation for the year 2000
Date:
UNEP/OzL.Pro/ExCom/29/7, Corr.1 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/29/8 Consequences of project cancellation
Date:
UNEP/OzL.Pro/ExCom/29/9 Completed projects with balances
Date:
UNEP/OzL.Pro/ExCom/29/10 Status report on ODS phase-out in Article 5 countries: Implementation of Decision 28/25
Date:
UNEP/OzL.Pro/ExCom/29/11 Consolidated draft business plan of the Multilateral Fund for the year 2000
Date:
UNEP/OzL.Pro/ExCom/29/12 Draft business plan for the year 2000 of UNDP
Date:
UNEP/OzL.Pro/ExCom/29/13 Draft business plan for the year 2000 of UNEP
Date:
UNEP/OzL.Pro/ExCom/29/14 Draft business plan for the year 2000 of UNIDO
Date:
UNEP/OzL.Pro/ExCom/29/15 Draft business plan for the year 2000 of World Bank
Date:
UNEP/OzL.Pro/ExCom/29/16 Proposed budget of the Fund Secretariat for the year 2000
Date:
UNEP/OzL.Pro/ExCom/29/17 Report of the Eighteenth Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/29/18, Corr.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/29/55 Revision of guidelines for the methyl bromide sector
Date:
UNEP/OzL.Pro/ExCom/29/57 Report of the Executive Committee’s subgroup on the production sector
Date:
UNEP/OzL.Pro/ExCom/29/58 Report of the contact group on refrigerant management plans
Date:
UNEP/OzL.Pro/ExCom/29/59 Concessional lending
Date:
UNEP/OzL.Pro/ExCom/29/60 Report on the implementation of the new administrative cost regime
Date:
UNEP/OzL.Pro/ExCom/29/61 Report of the Chair of the working
group on the phase-out plan for the solvent
sector in
Date:
UNEP/OzL.Pro/ExCom/29/65 Report of the Twenty-ninth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/29/65, Annex II Schedules of submissions of backlogged project completion reports
Date:
UNEP/OzL.Pro/ExCom/29/65, Annex V Agreed conditions for phase out of methyl bromide in Jordan
Date:
UNEP/OzL.Pro/ExCom/29/65, Annex VI Consensus Agreement for the Indian
Production Sector (
Date:
UNEP/OzL.Pro/ExCom/30/4 Report of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/30/5 Final report on the 1999 evaluation of refrigeration projects and draft follow-up action plan
Date:
UNEP/OzL.Pro/ExCom/30/6 and Corr. 1 Final report on the 1999 evaluation of institutional strengthening projects and draft follow-up action plan
Date:
UNEP/OzL.Pro/ExCom/30/7 Report of the workshop on project completion report formats
Date:
UNEP/OzL.Pro/ExCom/30/8 Desk study on evaluation of regional networks (2000 monitoring and evaluation work programme)
Date:
UNEP/OzL.Pro/ExCom/30/9 The possibility of a desk study on recovery and recycling projects
Date:
UNEP/OzL.Pro/ExCom/30/10 and Corr.1 Consolidated 2000 business plan of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/30/16 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/30/17 Completed projects with balances, follow-up on Decision 29/9
Date:
UNEP/OzL.Pro/ExCom/30/18 Financial intermediaries/administrative costs, follow-up on Decision 29/73
Date:
UNEP/OzL.Pro/ExCom/30/19 Sectoral ODS consumption data: consolidated report based on preliminary reports from Implementing Agencies (Decisions 28/25 and 29/10)
Date:
UNEP/OzL.Pro/ExCom/30/20 Report of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/30/21/Rev.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/30/34 Phase-out strategy
for the solvent sector in
Date:
UNEP/OzL.Pro/ExCom/30/35 Strategic planning and the draft three-year business plan for the Multilateral Fund for 2000-2002
Date:
UNEP/OzL.Pro/ExCom/30/38 The Executive Committee’s Subgroup on Production Sector
Date:
UNEP/OzL.Pro/ExCom/30/41 Report of the Thirtieth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/30/41, Annex III Agreed Conditions for Funding Methyl Bromide Phase out Project in Argentina
Date:
UNEP/OzL.Pro/ExCom/30/41, Annex IV Agreement for ODS Phase
out in
Date:
UNEP/OzL.Pro/ExCom/31/4 Report of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/31/6 Completed projects with balances: follow-up to Decision 30/19
Date: 25 May 2000
UNEP/OzL.Pro/ExCom/31/7 Implementation delays: follow-up to Decisions 30/10 and 30/11
Date:
UNEP/OzL.Pro/ExCom/31/8 Consolidated progress report as at
Date: 30 May 2000
UNEP/OzL.Pro/ExCom/31/9 Progress report of bilateral
co-operation as at
Date: 30 May 2000
UNEP/OzL.Pro/ExCom/31/14 and Corr.1 Evaluation of the implementation of the 1999 business plans
Date:
UNEP/OzL.Pro/ExCom/31/15 ODS sector consumption data: follow-up on Decision 30/20
Date:
UNEP/OzL.Pro/ExCom/31/16 Institutional strengthening projects: follow-up to Decision 30/7 (f) and (g)
Date:
UNEP/OzL.Pro/ExCom/31/17 and Corr.1 Desk study on compressor projects
Date:
UNEP/OzL.Pro/ExCom/31/18 Desk study on recovery and recycling projects
Date:
UNEP/OzL.Pro/ExCom/31/19 Draft format for institutional strengthening terminal reports and extension requests: follow-up to Decision 30/8 (e) and (f)
Date:
UNEP/OzL.Pro/ExCom/31/20 Report on evaluation of training projects
Date:
UNEP/OzL.Pro/ExCom/31/21 Report of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/31/22 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/31/61 Report of the Thirty-first Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex III Terminal report for institutional strengthening projects
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex IV Extension of institutional strengthening projects. revised plan of action
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex VII Conclusions and recommendations of the World Bank OORG foam density report 2000
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex VIII Agreed conditions for funding methyl
bromide phase-out project in
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex IX Agreed conditions for funding methyl
bromide phase-out project in
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex X Guidelines for definition of the sub-sector for assembly, installation and charging of refrigeration equipment and the calculation of incremental operating costs
Date:
UNEP/OzL.Pro/ExCom/31/61, Annex XI Terms of reference for a study on alternatives to CFC in rigid foam applications
Date:
UNEP/OzL.Pro/ExCom/32/3 Report of the Twelfth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/32/5 Status report on the implementation of the fixed exchange-rate mechanism
Date:
UNEP/OzL.Pro/ExCom/32/6 Completed projects with balances
Date:
UNEP/OzL.Pro/ExCom/32/9 Additional status report on project implementation required by decisions 31/6 (c) and 31/7 (e) and (f)
Date:
UNEP/OzL.Pro/ExCom/32/10 Report on the evaluation of the implementation of the 1999 business plans: follow-up to decision 31/11
Date:
UNEP/OzL.Pro/ExCom/32/18 General principles for agreements between governments and Implementing Agencies on new and renewed institutional strengthening projects (decision 30/7 (c))
Date:
UNEP/OzL.Pro/ExCom/32/19, Corr.1, Add.1 Report on the implementation of the monitoring and evaluation work programme for the year 2000
Date:
UNEP/OzL.Pro/ExCom/32/20, Corr.1 Draft work programme for monitoring and evaluation for the year 2001
Date:
UNEP/OzL.Pro/ExCom/32/31 Draft guidelines for preparation of country programme updates
Date:
UNEP/OzL.Pro/ExCom/32/32 Draft agreement on the phase-out
strategy for the tobacco sector in
Date:
UNEP/OzL.Pro/ExCom/32/33 Draft guidelines and standard format for verification of ODS production phase-out
Date:
UNEP/OzL.Pro/ExCom/32/40, Corr.1 Revised guidelines for methyl bromide projects (Draft)
UNEP/OzL.Pro/ExCom/32/44, Corr.1 Report of the Thirty-second Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex V Criteria and rating scheme for overall assessment
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex VI Schedule for submission of outstanding project completion reports (PCRs) in 2001
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex VII Recommendations from training programmes
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex IX Agreed conditions for funding methyl
bromide phase-out project in
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex X Agreed conditions for funding methyl
bromide phase-out project in
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex XI Agreed conditions for funding methyl
bromide phase-out project in
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex XII Agreed conditions for funding methyl
bromide phase-out project in
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex XIII Agreement between the Government
of China and the Executive Committee on the phase out strategy
for the tobacco sector (Sector Plan) in
Date:
UNEP/OzL.Pro/ExCom/32/44, Annex XIV Revised strategy and guidelines for projects in the methyl bromide sector
Date:
UNEP/OzL.Pro/ExCom/33/3 Report of the Thirteenth Meeting on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/33/6 Final report on the evaluation of foam projects
Date:
UNEP/OzL.Pro/ExCom/33/7, Corr.1 Final report on the evaluation of regional networks
Date:
UNEP/OzL.Pro/ExCom/33/8, Corr.1 Consolidated 2001 business plan of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/33/14, Corr.1, Rev.1 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/33/15, Add.1 Completed projects with balances
Date:
UNEP/OzL.Pro/ExCom/33/16 General principles for agreements between Governments and Implementing Agencies on new and renewed institutional strengthening projects (follow-up to Decision 32/15)
Date:
UNEP/OzL.Pro/ExCom/33/17 Report of the Twenty-second Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/33/18 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/33/25 Pre-requisites for terminal phase-out in the refrigeration sector
Date:
UNEP/OzL.Pro/ExCom/33/27 Strategic framework for national sub-regional and regional customs training
Date:
UNEP/OzL.Pro/ExCom/33/29, Add.1 Draft guidelines for the preparation of country programme updates
Date:
UNEP/OzL.Pro/ExCom/33/30 Strategic planning (follow-up to Decision 32/75)
Date:
UNEP/OzL.Pro/ExCom/33/31 Status report on the study on alternatives to CFC in rigid foam applications
Date:
UNEP/OzL.Pro/ExCom/33/32 Report of the Thirty-third Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/33/32, Annex VII Draft prerequisites and guidelines for terminal phase-out in the refrigeration sector
Date:
UNEP/OzL.Pro/ExCom/33/32, Annex VIII Framework on the objectives, priorities, problems and modalities for strategic planning of the Multilateral Fund in the compliance period
Date:
UNEP/OzL.Pro/ExCom/34/4 Report of the Fourteenth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/34/5 Status report on the implementation of the fixed exchange mechanism (follow-up to Decision 32/2)
Date:
UNEP/OzL.Pro/ExCom/34/7 and Corr.1 Completed projects with balances
Date:
UNEP/OzL.Pro/ExCom/34/8 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/34/15 Evaluation of the implementation of the 2000 business plan
Date:
UNEP/OzL.Pro/ExCom/34/16 Status of Article 5 countries in achieving compliance with the initial control measures of the Montreal Protocol, an update by the Fund Secretariat (Decision 32/76)
Date:
UNEP/OzL.Pro/ExCom/34/17 Evaluation
of completed compressor projects in
Date:
UNEP/OzL.Pro/ExCom/34/18 Report of the Twenty-third Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/34/19 Issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/34/52 and Add.1 The use of the 13 per cent allowance for support costs (Decision 32/31)
Date:
UNEP/OzL.Pro/ExCom/34/53 Strategic planning
Date:
UNEP/OzL.Pro/ExCom/34/54 Guidelines for the preparation of country programme updates
Date:
UNEP/OzL.Pro/ExCom/34/56/Add.1 Production Sector
Date:
UNEP/OzL.Pro/ExCom/34/CRP.1 A Non-paper by
Date:
UNEP/OzL.Pro/ExCom/34/CRP.2 Concessional lending - a proposal from the Government of Japan
Date:
UNEP/OzL.Pro/ExCom/34/CRP.4 Comments by the Finnish delegation to the document on strategic planning: proposals on implementing the framework on the objective, priorities, problems, and modalities for strategic planning of the multilateral fund in the compliance period
Date:
UNEP/OzL.Pro/ExCom/34/CRP.5 Proposal by the Japanese delegation to the document on strategic planning: proposals on implementing the framework on the objective, priorities, problems, and modalities for strategic planning of the multilateral fund in the compliance period
Date:
UNEP/OzL.Pro/ExCom/34/58 Report of the Thirty-fourth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex VIII Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex X Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex XI Agreed conditions for phase-out
of methyl bromide in cut flowers in
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex XII Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex XIII Agreed conditions for the phase out of the
use of methyl bromide in grain storage
in
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex XIV Agreed conditions for phase-out
of methyl bromide in horticulture: tomatoes and cut
flowers in
Date:
UNEP/OzL.Pro/ExCom/34/58, Annex XV Consensus agreement for the Indian halon production and consumption sector
Date:
UNEP/OzL.Pro/ExCom/35/4 Report of the fifteenth meeting of the Sub-Committee of Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/35/5 Consolidated draft business plan of the Multilateral Fund for the year 2002
Date:
UNEP/OzL.Pro/ExCom/35/11 Report on the implementation of the monitoring and evaluation work programme for the year 2001
Date:
UNEP/OzL.Pro/ExCom/35/12 Final report on the evaluation of solvent sector projects
Date:
UNEP/OzL.Pro/ExCom/35/13 Draft monitoring and evaluation work programme for the year 2002
Date:
UNEP/OzL.Pro/ExCom/35/14 and Corr.1 Completed projects with balances
Date:
UNEP/OzL.Pro/ExCom/35/15 Implementation delays
Date:
UNEP/OzL.Pro/ExCom/35/16 Report on the performance indicators and proposal on modifications: follow-up to Decision 34/11
Date:
UNEP/OzL.Pro/ExCom/35/17 Progress reports: follow-up to Decisions 34/7 and 34/9
Date:
UNEP/OzL.Pro/ExCom/35/18 Proposed budget of the Fund Secretariat for the year 2002
Date:
UNEP/OzL.Pro/ExCom/35/19 Report of the twenty-fourth meeting of the Sub-Committee of Project Review
Date:
UNEP/OzL.Pro/ExCom/35/20 and Corr.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/35/60 Strategic planning of the Multilateral Fund revised document 34/53: follow-up to Decision 34/66 (c)
Date:
UNEP/OzL.Pro/ExCom/35/61 Study on defining a starting point for determining the remaining ODS consumption eligible for funding by the Multilateral Fund: follow-up to Decision 34/66 (a)
Date:
UNEP/OzL.Pro/ExCom/35/62 Draft decision on country programme update
Date:
UNEP/OzL.Pro/ExCom/35/63 Report of the Executive Committee’s Subgroup on production sector
Date:
UNEP/OzL.Pro/ExCom/35/66 Concessional lending: follow-up to Decision 34/69
Date:
UNEP/OzL.Pro/ExCom/35/67 Report of the Thirty-fifth Meeting of the Executive Committee of the Multilateral Fund for the Implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex III Budget for the Fund Secretariat for years 2002, 2003 and 2004
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex VI Compliance Assistance Programme (CAP) budget
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex VII Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex VIII Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex IX Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex X Agreed conditions for phase-out
of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XI Agreement for CFC phase out in the
polyurethane foam sector in
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XII Agreement for the terminal
CFC phase out management plan for the
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XIII Agreement for the national CFC phase out plan for Malaysia
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XIV Agreement for the national CFC phase out plan for Thailand
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XV Agreement for the total phase out of CFCs in Turkey
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XVI Adjusted funding policies of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/35/67, Annex XVII Format for country programme update
Date:
UNEP/OzL.Pro/ExCom/36/4 Report of the Sixteenth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date: February 2002
UNEP/OzL.Pro/ExCom/36/5, Corr.1, Corr.2 Report on the extended desk study on clearing house evaluation
Date: February 2002
UNEP/OzL.Pro/ExCom/36/6 Report on the desk study on MAC projects
Date: February 2002
UNEP/OzL.Pro/ExCom/36/8/Rev.1, Add.1 Consolidated 2002 business plan of the Multilateral Fund
Date: February 2002
UNEP/OzL.Pro/ExCom/36/14/Rev.1 Further modifications to resource allocations
Date: February 2002
UNEP/OzL.Pro/ExCom/36/15 and Corr.1 Implementation delays
Date: February 2002
UNEP/OzL.Pro/ExCom/36/16 Report of the Twenty-fifth Meeting on the Sub-Committee on Project Review
Date: February 2002
UNEP/OzL.Pro/ExCom/36/17/Rev.1 Overview of issues identified during project review
Date: February 2002
UNEP/OzL.Pro/ExCom/36/31 Funding of technology that is not in the public domain
Date: February 2002
UNEP/OzL.Pro/ExCom/36/32 Implementation of Decision 35/56
Date: February 2002
UNEP/OzL.Pro/ExCom/36/33, Add.1, Add.2 Report of the Executive Committee’s Subgroup on Production Sector
Date: February 2002
UNEP/OzL.Pro/ExCom/36/34 Report on the study on alternatives to CFC in rigid foam applications
Date: February 2002
UNEP/OzL.Pro/ExCom/36/35 Policy paper on issues surrounding the choice of HCFC-141b for conversion projects
Date:
UNEP/OzL.Pro/ExCom/36/36 Report of the Thirty-sixth meeting of the Executive Committee of the Multilateral Fund for the implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/36/36, Annex II to V Project performance indicators
Date:
UNEP/OzL.Pro/ExCom/36/36,
Annex IX Agreed conditions for
phase-out of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/36/36,
Annex X Amended agreement for the
phase-out in the ODS production
sector in Democratic People’s Republic of
Date:
UNEP/OzL.Pro/ExCom/36/36,
Annex XI Proposal by
Date:
UNEP/OzL.Pro/ExCom/36/36, Annex XII Terms of service of the Chief Officer of the Multilateral Fund Secretariat, Japanese proposal
Date:
UNEP/OzL.Pro/ExCom/37/4 Report of the Seventeenth Meeting of the Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/37/5 Status report on the evaluation of aerosol projects
Date:
UNEP/OzL.Pro/ExCom/37/6 Report on the desk study on halon projects
Date:
UNEP/OzL.Pro/ExCom/37/7 and Corr.1 Report on the information collected concerning the status of implementation of MAC projects: follow-up to Decision 36/3
Date:
UNEP/OzL.Pro/ExCom/37/11 Consolidated Progress Report
Date: June 2002
UNEP/OzL.Pro/ExCom/37/17 and Corr.1 Evaluation of the implementation of the 2001 business plans
Date:
UNEP/OzL.Pro/ExCom/37/18 and Corr.1 Update report on the status of Article 5 countries in achieving compliance with the initial control measures of the Montreal Protocol;
Date: June 2002
UNEP/OzL.Pro/ExCom/37/22 Report of the Twenty-sixth Meeting of the Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/37/23 and Corr.1 Issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/37/58 Draft guidelines for Metered Dose Inhaler (MDI) projects
Date:
UNEP/OzL.Pro/ExCom/37/59 Funding of technology that is not in public domain (follow up to Decision 36/52)
Date:
UNEP/OzL.Pro/ExCom/37/64 Selection of options pursuant to Decision 35/57
Date:
UNEP/OzL.Pro/ExCom/37/65 Guidelines for the preparation, implementation and management of performance-based substance-wide and national ODS phase-out agreements/plans
Date:
UNEP/OzL.Pro/ExCom/37/66 and Corr.1 Business planning: Resource planning and Resource allocations
Date:
UNEP/OzL.Pro/ExCom/Inf.2 Communication Strategy for Global Compliance with the Montreal Protocol (submitted by UNEP DTIE)
Date:
UNEP/OzL.Pro/ExCom/37/71 and Coor.1 Report of the Thirty-seventh meeting of the Executive Committee of the Multilateral Fund for the implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/37/71,
Annex III Agreement for the CFC
terminal phase-out management
plan for
UNEP/OzL.Pro/ExCom/37/71,
Annex IV Agreement for the total
phase-out of Annex A Group I substances (CFCs) in
UNEP/OzL.Pro/ExCom/37/71,
Annex VI Agreement for phase-out
of CFCs in the refrigeration (manufacturing) sector
in
UNEP/OzL.Pro/ExCom/37/71,
Annex VII Agreement for phase-out
of CFCs in the foam sector in
UNEP/OzL.Pro/ExCom/38/4 Report of the Meeting of the 18th Sub-Committee on Monitoring, Evaluation & Finance
Date:
UNEP/OzL.Pro/ExCom/38/5 and Corr.1 Final report on the evaluation of aerosol projects
Date:
UNEP/OzL.Pro/ExCom/38/6 Evaluation report on MAC
projects in
Date:
UNEP/OzL.Pro/ExCom/38/9 Project implementation delays
Date:
UNEP/OzL.Pro/ExCom/38/10 Project balances
Date:
UNEP/OzL.Pro/ExCom/38/13 Proposed budget of the Fund Secretariat for the year 2003
Date:
UNEP/OzL.Pro/ExCom/38/14 Report of the Meeting of the 27th Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/38/15 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/38/56 Refrigerant management plans and terminal phase-out management plans (Decision 37/70 (a))
Date:
UNEP/OzL.Pro/ExCom/38/57 and Rev.1 Revised guidelines for the preparation, implementation and management of performance-based sector and national ODS phase-out plans: follow-up to Decision 37/67
Date:
UNEP/OzL.Pro/ExCom/38/58 2003-2005 phase-out plan for the Multilateral Fund (Decision 37/68 (b))
Date:
UNEP/OzL.Pro/ExCom/38/59 Administrative support costs and agency shares
Date:
UNEP/OzL.Pro/ExCom/38/60 Performance indicators
Date:
UNEP/OzL.Pro/ExCom/38/65 Report of the Executive Committee’s Subgroup on Production Sector
Date:
UNEP/OzL.Pro/ExCom/38/67 and Corr.1 Report of the Fund Secretariat on the technical workshop on concessional lending (Decision 35/61)
Date:
UNEP/OzL.Pro/ExCom/38/68 Framework for an information strategy for the Multilateral Fund (Decision 37/1 (b))
Date:
UNEP/OzL.Pro/ExCom/38/69 Communication strategy for global compliance with the Montreal Protocol (Decision 37/72 (b))
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1 Report of the Thirty-eighth meeting of the Executive Committee of the Multilateral Fund for the implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1,
Annex V Agreement for the national CFC
phase-out plan for the
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1, Annex VIII Agreed conditions for phase-out of methyl bromide in Dominican Republic
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1,
Annex IX Agreed conditions for
phase-out of methyl bromide in
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1,
Annex X Agreement for the plan for
phase-out of CFCs in the refrigeration
(manufacturing) sector in
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1,
Annex XI Agreement for the plan
for phase-out of CFCs in the refrigeration
sector in
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1,
Annex XII Agreement for the
national CFC phase-out plan for
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1,
Annex XIII Agreement with the
People’s Republic of
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1, Annex XIV Guidelines on funding of technology not in the public domain
Date:
UNEP/OzL.Pro/ExCom/38/70/Rev.1, Annex XV Agreement for the Argentina Production Sector
Date:
UNEP/OzL.Pro/ExCom/39/6 Report of the meeting of the 19th Sub-Committee on Monitoring, Evaluation and Finance
Date:
UNEP/OzL.Pro/ExCom/39/7 Financial planning for the triennium 2003-2005
Date:
UNEP/OzL.Pro/ExCom/39/8/Rev.1 Consolidated 2003 business plan of the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/39/9 Corr.1/Rev.1 Corr.2 2003 business plans for bilateral agencies
Date:
UNEP/OzL.Pro/ExCom/39/10 and Corr.1 Business plan for the year 2003 of UNDP
Date:
UNEP/OzL.Pro/ExCom/39/11and Corr.1 Business plan for the year 2003 of UNEP
Date:
UNEP/OzL.Pro/ExCom/39/12 Business plan for the year 2003 of UNIDO
Date:
UNEP/OzL.Pro/ExCom/39/13 and Corr.1 Business plan for the year 2003 of the World Bank
Date:
UNEP/OzL.Pro/ExCom/39/14 Extended desk study on RMP evaluation
Date:
UNEP/OzL.Pro/ExCom/39/15 Results of the analysis of the current procurement procedures of the implementing agencies
Date:
UNEP/OzL.Pro/ExCom/39/19, Corr.1 and 2 Report of the meeting of the 28th Sub-Committee on Project Review
Date:
UNEP/OzL.Pro/ExCom/39/20 and Corr.1 Overview of issues identified during project review
Date:
UNEP/OzL.Pro/ExCom/39/38 and Corr.1 Liquid carbon dioxide (LCD) technology and guidelines for LCD projects
Date:
UNEP/OzL.Pro/ExCom/39/41 Information strategy for the Multilateral Fund
Date:
UNEP/OzL.Pro/ExCom/39/43 Report of the Thirty-ninth meeting of the Executive Committee of the Multilateral Fund for the implementation of the Montreal Protocol
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex II 2003 business
plan performance
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex III 2003 business
plan performance
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex IV 2003 business
plan performance
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex V 2003 business
plan performance
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex VII Agreement for the
terminal ODS phase out management
plan (TPMP) for
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex VIII Agreement for the terminal
CFC phase out management plan (TPMP) for
Date:
UNEP/OzL.Pro/ExCom/39/43,
Annex X Agreement for the
national phase out plan for
Date:
I. Meetings
of the Parties to the
First...............................................
Second........................................... London....................... 27-29 June 1990
Third.............................................
Fourth............................................ Copenhagen.......... 23-25 November 1992
Fifth..............................................
Sixth..............................................
Seventh..........................................
Eighth............................................
Ninth.............................................
Tenth.............................................
Eleventh.........................................
Twelfth..........................................
Thirteenth.......................................
Fourteenth......................................
II. Meetings of the Executive Committee of the
Multilateral Fund for the Implementation of the
First...............................................
Second...........................................
Third.............................................
Fourth............................................
Fifth..............................................
Sixth..............................................
Seventh..........................................
Eighth............................................
Ninth.............................................
Tenth.............................................
Eleventh.........................................
Twelfth..........................................
Thirteenth.......................................
Fourteenth......................................
Fifteenth.........................................
Sixteenth........................................
Seventeenth....................................
Eighteenth .....................................
Nineteenth......................................
Twentieth.......................................
Twenty-first...................................
Twenty-second...............................
Twenty-third..................................
Twenty-fourth................................
Twenty-fifth...................................
Twenty-sixth..................................
Twenty-seventh..............................
Twenty-eighth................................
Twenty-ninth..................................
Thirtieth.........................................
Thirty-first.....................................
Thirty-second.................................
Thirty-third.....................................
Thirty-fourth..................................
Thirty-fifth.....................................
Thirty-sixth....................................
Thirty-seventh................................
Thirty-eighth...................................
Thirty-ninth....................................
[1] Paragraph 3 (UNEP XE "UNEP" /OzL.Pro/ExCom/34/53): The Secretariat is fully conscious that this exercise of introducing changes is proposed to be made in the modus operandi of an institution which has been in operation XE "operation" for over 10 years and therefore proposes to take the following approach:
(a) build on the existing infrastructure: Changes are proposed only after an in-depth review of the existing system to identify any specific deficiencies with a view to rectifying them to make the system function more effectively under the new circumstances;
(b) determine an appropriate transitional XE "transitional" period: Since changes must be introduced without interrupting the momentum which has been created in the grace period, adequate time should be made available for the various partners involved to get acquainted with, and implement the changes;
(c) introduce changes step-wise: The policies, guidelines XE "guidelines" and operating procedures XE "procedures" of the Fund have evolved over the yeas into an organic whole and at the same time follow a sequence either on the basis of substance or operational need. For instance the funding policies will determine the kind of implementation modalities and operational guidelines to support the policies, which will in turn, determine the operating procedures that have to be adopted. This will be the sequence that these issues will be reviewed and introduced. As a result the current paper will not address the various operating procedures and business XE "business" practices, like the performance XE "performance" indicators of business plans, however they will have to be reviewed to determine their continued relevance in light of new operating policies and operating modalities of the Fund.
[2] List of products and equipment XE "equipment" containing a controlled substance specified in Annex A or B of the Montreal Protocol XE "Montreal Protocol" : 1) automobile and truck air conditioning units (whether incorporated in vehicles or not); 2) domestic and/or commercial XE "commercial" refrigeration XE "commercial refrigeration" and air conditioning/heat pump equipment (when containing controlled substances XE "controlled substances" in Annex A or Annex B as a refrigerant XE "refrigerant" and/or in insulating material of the product) (e.g. refrigerators, freezers, dehumidifiers, water coolers, ice machines, air conditioning and heat pump units); 3) transport refrigeration XE "refrigeration" XE "transport refrigeration" units; 4) aerosol XE "aerosol" products, except medical aerosols XE "aerosols" ; 5) portable fire extinguisher; 6) insulation boards, panels and pipe covers; 7) pre-polymers.
[3] Project documents represent agreements for some agencies.
[4] The technology license fee is not subject to 10% contingency XE "contingency" .
[5] +10% contingency XE "contingency" to be added.
[6] Where it is not feasible to lease the LCD tank, the cost of a tank in the range of US $15,000 - US $25,000 may be included in the capital costs XE "capital costs" .
* These costs may be omitted if they do not change significantly before and after conversion XE "conversion" .
1 Subject to further analysis and verification, including detailed process calculations if necessary. Field Audit should collect data for such analysis and rule XE "rule" out sites for expansion, conversion XE "conversion" and/or revamp based on field factors such as, space limitations, limited access to raw material XE "raw material" s XE "raw materials" , etc.
[7] Estimates of additional staff time required.
[8] 65 per cent of 1995 production XE "production" of halon XE "halon" extinguishers plus 1995 production of CO2 XE "CO2" extinguishers.