Home TOC Index Previous Next

Follow-up on the evaluation reports on foam projects

The Thirty-fifth Meeting of the Executive Committee decided:

(a)  that the focus should be on lessons learned from the foam evaluation and their application in the development of future projects;

(b)  to request the Secretariat and the Implementing Agencies to use observed actual average project duration as a starting point for determining on a case-by-case basis the duration of foam projects converting to HCFC-141b technology;

(c)  to take note of the report on fire incidences reported in some foam conversion projects.

(UNEP/OzL.Pro/ExCom/35/67, Decision 35/9, para. 35).