China’s production sector

The Twenty-seventh Meeting of the Executive Committee decided:

(a)  to approve the proposed Agreement for the China Production Sector, as contained in Annex XII.31 to the present report;

(b)  to request the Sub-Committee on Project Review to monitor the implementation of the Agreement in accordance with its terms and report any discrepancies to the Executive Committee, on the basis of the annual work programmes and the requests for funding by the World Bank;

(UNEP/OzL.Pro/ExCom/27/48, Decision 27/82(a b), para. 120 (a, b)).

The Twenty-eighth Meeting of the Executive Committee decided:

(a)  to approve the remaining US $10 million in the 1999 tranche for implementation of the Agreement for the China Production Sector with the understanding that disbursement of these funds by the World Bank would be contingent on the verification by the World Bank for the Executive Committee in accordance with the World Bank’s responsibilities in the Agreement demonstrating that the initial reductions required by the Agreement had been met;

(b)  to request the World Bank to transmit a report to the Secretariat for onward transmission to the Executive Committee on the understanding that disbursement of this US $10 million would take place if no objection was received by the Secretariat within 15 business days of the dispatch of the report;

(UNEP/OzL.Pro/ExCom/28/57, Decision 28/51, para. 97 (a, b)).

The Twenty-ninth Meeting of the Executive Committee decided:

(a)  to note that the request for funding for the 2000 annual programme would be submitted at its first Meeting in 2000; and

(b)  to request the World Bank to include in its inspection report on the implementation of component 2 of the 1999 programme: the name of the plant and the plant identification number used in the SRIC audit report; CFCs produced; capacity; production level of the year preceding closure (CFC-11, CFC-12 and CFC-113 reported separately); production to be closed/reduced; balance to remain in production.

(UNEP/OzL.Pro/ExCom/29/65, Decision 29/27, para. 55).

The Thirty-eighth Meeting of the Executive Committee decided:

(a)  to approve the 2003 work programme of the China CFC production closure programme and withhold the requested funding until the World Bank had submitted to the 39th Meeting a satisfactory verification report on the implementation of the 2002 annual programme;

8.       to apply 7.5 per cent as agency support cost for the funds to be approved from the 2003 work programme, consistent with Decision 38/68.

(UNEP/OzL.Pro/ExCom/38/70/Rev.1, Decision 38/44, para. 80).