
SECTION 1: PROJECT OVERVIEW
*Indicate whether this report is provisional FORMCHECKBOX
SECTION 2: Criteria and Rating Scheme for Overall assessment
*The overall rating will be calculated only if the pre-conditions for completion as defined by the Executive Committee in Decision 28/2 are met and documented (applicable for projects completed after July 1999).
**Please rate the project performance with regard to quality/appropriateness using the following scale for each category: Highly satisfactory: (5); Satisfactory: (3); Less satisfactory: (1).
SECTION 3: DESCRIPTIVE ASSESSMENT OF PROJECT PERFORMANCE
The following questions are to summarize actual performance as compared to what was approved in the project document.
3.1 Comments on ODS phase-out approved and achieved (explain differences, report on remaining consumption of ODS and the risk of the beneficiary returning to the use of ODS):
3.2 Explain reasons if conversion technology was changed after approval (in cases other than approved by the Executive Committee):
3.3 Describe any major (technical, financial, political or other) problems encountered in project preparation, causes of delays and actions taken to overcome them:
3.4 Describe main post-conversion safety and environmental risks and measures taken to cope with them; attach copies of appropriate certificates:
3.5 Report on implementation of Executive Committee approval conditions (in cases of approval with specified conditions):
3.6 Comments on differences between approved and actual figures for capital, operational and contingency costs and actions taken to cope with cost overruns:
3.7 Report on reasons for changes in counterpart funding for eligible incremental costs:
3.8 Categorize and describe causes of implementation delays and actions taken to overcome them:
|
Categories |
Causes of Delay |
Actions taken to Overcome Delay(s) |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
3.9 Provide an overall assessment of the fate of the baseline equipment (refer to Section 7):
3.10 Lessons learned for future action:
3.11 Comments of the beneficiary enterprise:
3.12 Government's / NOU's comments:
Pre-conversion (as reported in project document).
4.1 Products manufactured/services provided:
4.2 Annual level of production / services:
4.3 ODS consumed in baseline year:
|
Substance |
Amount in tonnes |
||
|
0.00 |
0.00 |
0.00 |
|
|
0.00 |
0.00 |
0.00 |
|
|
0.00 |
0.00 |
0.00 |
|
|
0.00 |
0.00 |
0.00 |
|
|
Total: |
0.00 |
|
0.00 |
|
Explanations, if needed: |
|||
4.4 Project Preparation
Transition from ODS-based to non-ODS-based production/services
4.5 Evolution of the amount of ODS consumed
|
Schedule |
Actual Year |
|||||
|
199X* |
|
|
|
|
|
|
|
199X** |
|
|
|
|
|
|
|
199X+1 |
|
|
|
|
|
|
|
199X+2 |
|
|
|
|
|
|
|
199X+3 |
|
|
|
|
|
|
|
199Y*** |
|
|
|
|
|
|
|
200Y+1**** |
|
|
|
|
|
|
|
Explanations, if needed:
|
||||||
4.6 Evolution of the amount of substitutes consumed
|
Schedule |
Actual Year |
|||||
|
SUB(1) |
SUB(2) |
SUB(3) |
SUB(4) |
|||
|
199X* |
|
|
|
|
|
|
|
199X** |
|
|
|
|
|
|
|
199X+1 |
|
|
|
|
|
|
|
199X+2 |
|
|
|
|
|
|
|
199X+3 |
|
|
|
|
|
|
|
199Y*** |
|
|
|
|
|
|
|
200Y+1**** |
|
|
|
|
|
|
|
Explanations, if needed:
|
||||||
*Baseline year (per project document).
**Year of project approval. Please adjust accordingly if baseline year = approval year
***Year of successful commencement of new projection.
****Most recent year.
4.7 Amount of substitutes consumed in final year of report, and remaining Ozone Depleting Potential
|
Substitute |
Amount in Tonnes |
||
|
SUB (1) |
0.00 |
0.00 |
0.00 |
|
SUB (2) |
0.00 |
0.00 |
0.00 |
|
SUB (3) |
0.00 |
0.00 |
0.00 |
|
SUB (4) |
0.00 |
0.00 |
0.00 |
|
Total: |
0.00 |
|
0.00 |
|
Explanations, if needed:
|
|||
SECTION 5: BUDGET AND EXPENDITURES
In case this PCR is still provisional (as indicated in Section 1), this may serve as a status report on project expenditures at the time of preparing the Project Completion Report with the understanding that a full financial completion report will be prepared as a supplement once the accounts of the project are closed.
5.1 Total budget and expenditure on incremental cost:
*If IOC funds were used to finance incremental capital costs, in accordance with ExCom Decision 20/6, the amount should be specified in Section 3.6 above.
**Differences between total approved costs and total MLF grant may be due to non-Art. 5 country ownership and/or exports to Art. 2 countries (see Sections 1.11 and 1.12 above).
5.2 Detailed list of incremental capital cost and contingency by item:
|
Approved costs |
Actual costs |
Actual funding |
||
|
|
|
|
Grant funds |
Counterpart funds |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Subtotal |
|
|
|
|
|
Contingency |
|
|
|
|
|
Explanations, if needed: |
||||
*List of equipment capital cost, including cost for international consultants by item as approved in project document (additional equipment should be indicated). If the company insists on purchasing equipment for more than the limits established through international bidding please provide detailed explanation in Section 3.6.
5.3 Incremental Operating Costs by Item and Disbursement(s)
|
|
As per project document approved |
||
|
Cost Items |
Before |
After |
Actual |
|
$ 0.00 |
|
|
|
|
Substitute prices US$/kg (per substance) |
|
$ 0.00 |
$ 0.00 |
|
Compressor prices US$/unit* |
$ 0.00 |
$ 0.00 |
$ 0.00 |
|
0.00 |
0.00 |
0.00 |
|
|
Other (please specify) |
|
|
|
|
Explanations, if needed: |
|||
*Where applicable
5.4 Approved and actual incremental operating costs: (To be filled only upon specific request by the Multilateral Fund Secretariat)
|
|
As per project document approved |
||
|
Item |
Before |
After |
Actual |
|
Number of units produced (annually) |
0.00 |
|
0.00 |
|
Incremental unit costs US$/unit* |
$ 0.00 |
$ 0.00 |
$ 0.00 |
|
$ 0 |
$ 0 |
$ 0 |
|
|
Duration (years) |
0 |
|
0 |
|
$ 0 |
$ 0 |
$ 0 |
|
|
Explanations, if needed: |
|||
*Present the calculation of the actual incremental unit cost in the box below or attach it.
5.5 Counterpart funding of additional items not included in the project document (based on information provided by the company/beneficiary):
|
|
Items |
Actual expenditures |
|
1. |
|
|
|
2. |
|
|
|
3. |
|
|
|
Total |
|
|
|
Explanations, if needed: |
||
SECTION 6: IMPLEMENTATION EFFICIENCY
*Completion of project refers to when ODS-free production starts and equipment has been destroyed per ExCom Decision 28/2(a).
**The number of months taken to complete item by item
SECTION 7: FATE OF ODS-BASED PRODUCTION EQUIPMENT
*List of equipment to be rendered unusable or to be modified according to the project document
**Description/specification should include model and serial numbers
****Attach copy of certificate
(UNEP/OzL.Pro/ExCom/30/41, Decision 30/8, para. 25).
(UNEP/OzL.Pro/ExCom/32/44, Decision 32/18, para. 29).
(Supporting document: UNEP/OzL.Pro/ExCom/30/7).
(Supporting document: UNEP/OzL.Pro/ExCom/32/19, Corr.1 and Add.1).
