The
Twenty-eighth Meeting of the Executive Committee decided:
(a) that project balances should be returned to
the Multilateral Fund at the latest 12 months after project completion;
(b) to request Implementing Agencies to report to
the Executive Committee if they could not close the accounts on a project
within 12 months after project completion;
(c) also to request Implementing Agencies to
report to the Executive Committee cases where they could not liquidate their
remaining obligations within 12 months after project completion.
(UNEP/OzL.Pro/ExCom/28/57,
Decision 28/7, para. 21).
The
Twenty-ninth Meeting of the Executive Committee decided:
(a) to take note with appreciation of the report
of UNDP;
(b) to request a report from each agency, to be
submitted to the Thirtieth Meeting of the Executive Committee, on the extent to
which the Implementing Agencies’ share of the project balances from projects
completed through 1998 has been obligated;
(c) that where there were still balances that had
not been committed or obligated for projects completed by December 1997, those
amounts should be made available for utilization by the Executive Committee at
its Thirtieth Meeting.
(UNEP/OzL.Pro/ExCom/29/65,
Decision 29/9, para. ).
The
Thirtieth Meeting of the Executive Committee decided to request the Secretariat
to liaise with the Implementing Agencies to refine further the un-obligated
balances and un-liquidated obligations included in the following table and to
indicate a time for return of the balances to the Fund in time for the
Thirty-first Meeting.
|
Agency |
Balances
from completed projects through 1998 (US$) |
Obligations
(US$) |
Funds
to be returned (US$) |
Un-obligated
balances (US$) |
|
UNEP |
2,404,858 |
1,931,979 |
481,365 |
0 |
|
UNIDO |
7,287,129 |
4,652,911 |
336,091 |
2,134,079 |
|
World Bank |
11,319,764 |
3,296,410 |
5,350,629 |
5,969,134 |
|
Total |
21,011,751 |
9,881,300 |
6,168,085 |
8,103,213 |
(UNEP/OzL.Pro/ExCom/30/41, Decision
30/19, para. 40).
(Supporting document: UNEP/OzL.Pro/ExCom/30/17).
The
Thirty-second Meeting of the Executive Committee decided that balances from
completed recurring projects should be returned to the Fund for reprogramming.
(UNEP/OzL.Pro/ExCom/32/44,
Decision 32/3, para. 14
(c)).
The
Thirty-third Meeting of the Executive Committee decided:
(b) to urge Implementing Agencies to specify a
date on which funds would be returned for all projects;
(c) to note that UNIDO had indicated that it would
return US $700,000 of its US $2.2 million in unobligated balances
within one month, and that it would report on the schedule for returning funds
on 16 projects by the Thirty-fourth Meeting;
(d) to request the Multilateral Fund Secretariat
to ensure that UNIDO reported unobligated balances in the same way as the other
Implementing Agencies;
(e) to note with appreciation the reports on
completed projects with balances from the Governments of Australia, Canada,
Denmark, France, and the United States of America and the four Implementing
Agencies contained in UNEP/OzL.Pro/ExCom/33/15 and Add.1.
(UNEP/OzL.Pro/ExCom/33/32, Decision
33/11, para. 28 (b,
c, d, e)).
(Supporting documents:UNEP/OzL.Pro/ExCom/33/15 and
33/15/Add.1).
The
Thirty-fourth Meeting of the Executive Committee decided to request UNIDO and
the World Bank, at the 35th Meeting, to specify a date on which funds would be
returned for those projects where no date was specified, pursuant to Decision
33/11(b).
(UNEP/OzL.Pro/ExCom/34/58,
Decision 34/2, para. 20(b)).
The
Thirty-fifth Meeting of the Executive Committee decided to note with concern
that it appeared that projects had been prematurely classified as completed
although they had not been completed, and requested the agencies to adhere
strictly to Decision 28/2 when classifying all projects as completed.
(UNEP/OzL.Pro/ExCom/35/67,
Decision 35/12, para. 40
(c)).
The Thirty-eighth Meeting of the
Executive Committee decided:
(a) to
note:
(i) the report on project balances contained in
UNEP/OzL.Pro/ExCom/38/10;
(ii) the levels of funds being returned to the 38th
Meeting totaling US $3,751,490 including support costs as follows by
agency: US $283,783 from UNDP and agency support costs of US $30,468;
US $174,000 from UNEP and agency support costs of US $22,620;
US $1,770,088 from UNIDO and agency support costs of US $232,629, and
US $1,147,692 from the World Bank and agency support costs of
US $90,210;
(iii) that Implementing Agencies had balances
totaling US $2,422,895 excluding support costs from projects completed
over two years previously: UNDP (US $664,430 plus support costs); UNIDO
(US $1,547,147 plus support costs); and the World Bank (US $211,318
plus support costs);
(b) to
urge Implementing Agencies to re-assess the status of their completed projects
with balances and re-classify projects as ongoing in their reports to the 39th
Meeting if Decision 28/2 had not been fully complied with and reconsider the
matter if balances from projects completed two years previously did not
continue to be reduced;
(c) to
withhold US $1,159,980 from fund transfers to the World Bank at the 38th
Meeting as the World Bank had not provided sufficient explanations for not
returning those support costs and any further consideration of the matter
should be made contingent on the World Bank providing information required by
the Secretariat for its assessments of the Bank’s compliance with Decision
35/13(k);
(d) to note that the only
circumstances under which it would be possible for a portion of the support
costs from cancelled projects and completed projects with savings not to be
returned according to United Nations practice was when a fee was paid by the
Implementing Agency to a financial intermediary to undertake a financial
evaluation of the enterprise before project implementation, and the project was
subsequently cancelled.
(UNEP/OzL.Pro/ExCom/38/70/Rev.1, Decision 38/7, para. 38).
The
Forty-first Meeting of the Executive Committee decided to note:
(i) the
report on project balances contained in document UNEP/OzL.Pro/ExCom/41/11;
(ii) the
levels of funds being returned to the Forty-first Meeting, totaling
US $3,442,269 plus support costs of US $446,975 as follows by agency:
US $1,337,614 from UNDP and agency support costs of US $173,252,
including reimbursement of funds previously returned in error for two projects
by UNDP; US $364,882 from UNEP and agency support costs of
US $47,435; US $601,841 from UNIDO and agency support costs of
US $78,237, including reimbursement of funds for 17 projects due to
necessary adjustments to reconcile the accounts; and US $1,137,932 from
the World Bank and agency support costs of US $148,051;
(iii) that
Implementing Agencies had balances totaling US $408,477, excluding support
costs from projects completed over two years previously: UNDP (US $255,399
plus support costs); UNEP (US $62,610 plus support costs); and the World
Bank (US $90,468 plus support costs); and
(iv) that
the Government of Israel had returned US $64,177 plus support costs of
US $5,847 by making a cash contribution to the Treasurer for the
international methyl bromide compliance assistance workshop
(GLO/FUM/37/TRA/240).
(UNEP/OzL.Pro/ExCom/41/87, Decision 41/9, para.40(a) ).
(Supporting documents:UNEP/OzL.Pro/ExCom/41/11).
The Forty-second Meeting of the
Executive Committee decided:
(a) to
note both the level of funds being returned to the 42nd Meeting against project
balances totaling US $2,574,926: UNDP - US $526,643 including
reimbursement of funds previously returned in error for two projects; UNIDO -
US $1,048,283; and the World Bank - US $1,000,000; and additionally
the return of support costs totaling US $280,891: UNDP - US $68,463
including reimbursement of support costs previously returned in error for two
projects; UNIDO - US $117,428; and the World Bank - US $95,000; and
(b) also
to note that Implementing Agencies had balances totaling US $513,207
excluding support costs from projects completed over two years previously: UNDP
- US $388,882 plus support costs; UNEP - US $33,857 plus support
costs; and the World Bank - US $90,468 plus support costs.
(UNEP/OzL.Pro/ExCom/42/54,
Decision 42/16, para. 72)
(Supporting documents:UNEP/OzL.Pro/ExCom/42/2 Annex I).
The
Forty-third Meeting of the Executive Committee decided:
(a) to note:
(i) the
report on project balances contained in document UNEP/OzL.Pro/ExCom/43/4;
(ii) the
levels of funds being returned to the 43rd Meeting against project balances
totalling US $960,388 (UNDP US $617,556 net of reimbursement of funds
previously returned in error for six projects by UNDP; UNEP US $214,930;
UNIDO US $27,470; and the World Bank US $100,432 net of the funds
returned by UNDP for the Thai institutional strengthening project to be
transferred to the World Bank), and additionally the return of support costs
totalling US $107,885 (UNDP US $80,078 net of reimbursement of
support costs previously returned in error for six projects by UNDP; UNEP
US $19,289; UNIDO US $3,484; and the World Bank US $5,034 net of
reimbursement of support costs associated with the transfer of the Thai
institutional strengthening project);
(iii) that
Implementing Agencies had balances totalling US $1,093,535 excluding
support costs from projects completed over two years previously as follows:
UNDP (US $808,118 plus support costs); and the World Bank
(US $285,417 plus support costs);
(iv) that
US $41,950,720 was available to the Executive Committee for approvals at
the 43rd Meeting; and
(b) to present future reports on balances and on
the availability of resources, noting the balances of unliquidated obligations
emanating from multi-year agreements which could not be returned.
(UNEP/OzL.Pro/ExCom/43/61,
Decision 43/2, para. 35).
(Supporting documents:UNEP/OzL.Pro/ExCom/43/4 I).
The
Forty-fifth Meeting of the Executive Committee decided:
(a) to note:
(i) the
report on project balances contained in document UNEP/OzL.Pro/ExCom/45/4;
(ii) the
net level of funds being returned from the multilateral Implementing Agencies
to the 45th Meeting against project balances totalling US $4,222,859,
including the return of US $263,533 from UNDP; US $40,000 from UNEP;
US $485,945 from UNIDO; and US $3,433,381 from the World Bank;
(iii) the
net level of support costs being returned from the multilateral Implementing
Agencies to the 45th Meeting against project support cost balances totalling
US $519,343, including the return of US $33,923 from UNDP;
US $5,200 from UNEP; US $59,063 from UNIDO; and US $421,157 from
the World Bank;
(iv) that
multilateral Implementing Agencies had balances totalling US $47,929,
excluding support costs, from projects completed over two years previously:
UNDP US $42,611 plus support costs; and UNEP US $5,318 plus support
costs; and that the amount of balances from such projects was the lowest
achieved since such balances began to be monitored by the Executive Committee
at its 28th Meeting;
(v) the
return of US $110,352 from UNDP on behalf of Australia, including earnings
on interest amounting to US $68,190, for the completed recovery and
recycling project in Viet Nam (VIE/REF/20/DEM/14), and the treasurer’s
adjustments to Australia’s bilateral contributions and cash contributions, and
that the interest was credited as interest collected on Fund balances instead
of additional contributions from Australia;
(b) to request the treasurer to offset the return
of US $75,353 to Germany from the Azckon refrigeration project in the
Philippines (PHI/REF/23/INV/53);
(c) to note that Germany would transfer the
interest amounting to US $36,710 to the treasurer, which should be
credited as interest collected on Fund balances instead of additional
contributions from Germany; and
(d) to note that US $88,629,484 was available
to the Executive Committee for approvals at the 45th Meeting.
(UNEP/OzL.Pro/ExCom/45/55,
Decision 45/3, para. 32).
(Supporting documents:UNEP/OzL.Pro/ExCom/45/4).
The
Forty-sixth Meeting of the Executive Committee decided to note:
(a) the report on project balances contained in
UNEP/OzL.Pro/ExCom/46/4;
(b) the net level of funds being returned by the
multilateral Implementing Agencies to the 46th Meeting against project balances
totalling US $1,983,485, including the return of US $69,845 from
UNDP; US $1,216,495 from UNEP; US $18,797 net of reimbursement of
funds previously returned twice for one project from UNIDO; and
US $678,348 from the World Bank;
(c) the net level of support costs being returned
by the multilateral Implementing Agencies to the 46th Meeting against project
support cost balances totalling US $246,548, including the return of
US $9,040 from UNDP; US $142,965 from UNEP; US $6,362 net of
reimbursement of support costs previously returned twice for one project by
UNIDO; and US $88,181 from the World Bank;
(d) that Implementing Agencies had balances
totalling US $2,940,519 excluding support costs from projects completed
over two years previously: UNDP US $484,719 plus support costs;
UNEP--US $40,063 plus support costs; and the World Bank--US $2,415,737
plus support costs; and
(e) that US $91,985,148 was available to the
Executive Committee for approvals at the 46th Meeting.
(UNEP/OzL.Pro/ExCom/46/47,
Decision 46/2, para. 24).
(Supporting documents:UNEP/OzL.Pro/ExCom/46/4).
The
Forty-eighth Meeting of the Executive Committee decided to note:
(a) the report on balances and availability of
resources contained in documents UNEP/OzL.Pro/ExCom/48/4 and Add.1;
(b) the net level of funds being returned by the
multilateral implementing agencies to the 48th Meeting against project balances
totalling US $751,179 that included the return of: US $372,434 from
UNDP; US $136,537 net of reimbursement of funds previously returned in
error for three projects from UNEP; US $247,596 from UNIDO; and US $5,388
reimbursement to the World Bank to account for the funds previously returned in
error for one project;
(c) the net level of support costs being returned
by the multilateral implementing agencies to the 48th Meeting against project
support cost balances totalling US $77,291 that included the return of:
US $46,296 from UNDP; US $10,279 net of reimbursement of support
costs previously returned in error for three projects from UNEP;
US $28,323 from UNIDO; and US $7,607 reimbursement to the World Bank
to account for the support costs previously returned in error for one project;
(d) that implementing agencies had balances
totalling US $11,812,361, excluding support costs from projects completed
over two years previously: UNDP US $824,798 plus support costs; UNEP
US $119,467 plus support costs; UNIDO US $165,063 plus support costs;
and the World Bank US $10,703,033 plus support costs;
(e) the transfer of US $114,480 plus agency
fees of US $10,303 from the World Bank to UNDP for the project “Phase-out
of CTC as process agent in the elimination of nitrogen trichloride during
chlorine production at Prodesal S.A.” (COL/PAG/47/INV/64) and to request the
Treasurer to make the necessary adjustments;
(f) that US $192,547 plus agency support
costs of US $25,031 in bilateral cooperation for Germany approved in the
2003 to 2005 triennium for the national ODS phase-out plan in Cuba, including
US $116,000 plus agency support costs of US $15,080 from the 2005
annual implementation plan (CUB/PHA/45/INV/30), as well as US $76,547 plus
agency support costs of US $9,951 from the first tranche of the plan
(CUB/PHA/43/TAS/25), should be offset against future approvals for Germany;
(g) that US $319,681 plus agency support
costs of US $41,559 in bilateral cooperation for France, approved in the
2003 to 2005 triennium for the national ODS phase-out plan in Cuba, including
US $200,000 plus agency support costs of US $26,000 approved at the
45th Meeting for the 2005 annual implementation plan (CUB/PHA/45/INV/31), as
well as the remaining balance of funds totalling US $119,681 plus agency
support costs of US $15,559 approved for the first tranche of the plan
(CUB/PHA/43/TAS/27), should be offset against approvals for France;
(h) the transfer of US $20,000 plus agency
fees of US $1,500 from UNDP to UNIDO for project preparation for a
fumigant (methyl bromide) project in Zimbabwe (ZIM/FUM/45/PRP/31) and to
request the Treasurer to make the necessary adjustment; and
(i) that US $41,771,843 was available to the
Executive Committee for approvals at the 48th Meeting.
(UNEP/OzL.Pro/ExCom/48/45, Decision
48/2, para. 28).
(Supporting documents:UNEP/OzL.Pro/ExCom/48/4 and Add.1).
The Forty-ninth Meeting of the
Executive Committee decided:
(a) the report on balances and availability of resources contained in
document UNEP/OzL.Pro/ExCom/49/4 and Add.1;
(b) the net level of funds being returned by the multilateral
implementing agencies to the 49th Meeting against project balances totalling
US $4,324,771, including the return of US $650,450 from UNDP,
US $50,803 from UNEP, US $216,855 from UNIDO, and US $3,406,663
from the World Bank;
(c) the net level of support costs being returned by the multilateral
implementing agencies to the 49th Meeting against project support cost balances
totalling US $532,132, including the return of US $82,209 from UNDP,
US $12,076 from UNEP, US $26,190 from UNIDO, and US $411,657
from the World Bank;
(d) that implementing agencies had balances totalling
US $14,550,486 excluding support costs from projects completed over two
years previously, including US $366,760 plus support costs from UNDP,
US $258,155 plus support costs from UNEP, US $223,151 plus support
costs from UNIDO, and US $13,702,420 plus support costs from the World
Bank; and
(e) that
US $31,529,502 was available to the Executive Committee for approvals at
the 49th Meeting.
(UNEP/OzL.Pro/ExCom/49/43, Decision
49/3, para. 36).
(Supporting documents:UNEP/OzL.Pro/ExCom/49/4 and Add.1).