1. This Agreement represents the understanding
of China (the “Country”) and the Executive Committee with respect to the
Accelerated Phase-out Plan (APP) of production and controlled use of ozone
depleting substances in the sectors set out in Appendix 1-A (the “Substances”)
by July 1, 2007 for CFC production and consumption and by January 1, 2010 for
halon 1301, in compliance with Protocol schedules. This Agreement supplements
the Agreements between the Executive Committee and China entered into (1) at
the 23rd Meeting for phase out of halons in the halon sector, (2) at the 27th
Meeting for the phase out of CFC production in China, and (3) at the 35th
Meeting for the phase out of CFCs in the polyurethane foam sector in China.
2. The Country agrees to phase-out the
production and the controlled use of the Substances in accordance with the
annual phase-out targets set out in row 1 to 9 of Table 1 in Appendix 2-A (the
“Targets”) of this Agreement. The other conditions in the existing agreements
on phase out of the Substances for the different sector plans in China will not
be changed with one exception for the Halon Sector Plan , and sector annual
programmes will be prepared. The annual phase out targets will, at a minimum,
correspond to the reduction schedules mandated by the Montreal Protocol. The
Country accepts that, by its acceptance of this Agreement and performance by
the Executive Committee of its funding obligations described in paragraph 3, it
is precluded from applying for or receiving further funding from the
Multilateral Fund in respect to the production and controlled use of phase-out
of CFCs and halon-1301, with the exception of the two remaining sector plans
which are under preparation, i.e. phasing out CFCs in the manufacturing of
metered dose inhalers (MDIs) and phasing out CFCs in the pharmaceutical
aerosols.
3. Subject to compliance by the Country with its
obligations set out in this Agreement, the Executive Committee agrees in
principle to provide the funding set out in rows 2, 5, and 7 of Table 2 in
Appendix 2-A (the “Funding”) to the Country. The Executive Committee will, in
principle, provide this funding at the Executive Committee meetings specified
in Appendix 3 A (the “Funding Approval Schedule”).
4. The Country will meet the production limits for
each Substance as indicated in row 1, 5 and 7 and consumption limits as
indicated in row 2, 3, 6 and 8 in Table 1 in Appendix 2-A. It will also accept
independent verification by the relevant Implementing Agency of achievement of
these production limits as described in paragraph 8 of this Agreement.
5. The Executive Committee will not provide the
Funding in accordance with the Funding Disbursement Schedule unless the Country
satisfies the following conditions at least 30 days prior to the applicable
Executive Committee meeting set out in the Funding Disbursement Schedule:
(a) that
the Country has met the Target for the applicable year;
(b) that
the meeting of these Targets has been independently verified as described in
paragraph 8;
(c) that
the Country has substantially completed all actions set out in the last Annual
Implementation Programme; and
(d) that
the Country has submitted and received endorsement from the Executive Committee
for an annual implementation programme in the form of Appendix 4 A (the “Annual
Implementation Programmes”) in respect of the year for which funding is being
requested.
6. The Country will ensure that it conducts
accurate monitoring of its activities under this Agreement. The institutions
set out in Appendix 5-A (the “Monitoring”) will monitor and report on that
monitoring in accordance with the roles and responsibilities set out in
Appendix 5-A. This monitoring will also be subject to independent verification
as described in paragraph 8.
7. While the Funding was determined on the basis
of estimates of the needs of the Country to carry out its obligations under
this Agreement, the Executive Committee agrees that the Country may have the
flexibility to reallocate the approved funds, or part of the funds according to
the evolving circumstances to achieve the goals prescribed under this
Agreement. Reallocations which are considered as major changes should be
accounted for in the verification report and reviewed by the Executive
Committee.
8. The Country agrees to assume overall
responsibility for the management and implementation of this Agreement and of
all activities undertaken by it or on its behalf to fulfill the obligations
under this Agreement. The Country also agrees to establish policies and
enforcement mechanisms to control illegal ODS related activities as set out in
Appendix 9-A. In line with the request of the Government of United States of
America, which is the bilateral agency for the accelerated phase-out programme,
the World Bank has agreed to be the lead implementing agency (the “Lead IA”) in
respect of the Country’s activities under this Agreement. The Lead IA will be
responsible, with the cooperation of the Government of the United States of
America in respect of the accelerated phase-out programme, for carrying out the
activities listed in Appendix 6-A including but not limited to independent
verification. The Country also agrees to periodic evaluations, which will be
carried out under the monitoring and evaluation work programme of the
Multilateral Fund. The Executive Committee agrees, in principle, to provide the
Lead IA with the fees set out in rows 3, 6, 8 and 10 of Table 2 in Appendix
2-A.
9. Should the Country, for any reason, not meet
the Targets for the elimination of the Substance or otherwise does not comply
with this Agreement, then the Country agrees that it will not be entitled to
the Funding in accordance with the Funding Disbursement Schedule. In the
discretion of the Executive Committee, funding will be reinstated according to
a revised Funding Disbursement Schedule determined by the Executive Committee
after the Country has demonstrated that it has satisfied all of its obligations
that were due to be met prior to receipt of the next installment of Funding
under the Funding Disbursement Schedule. The Country acknowledges that the
Executive Committee may reduce the amount of the Funding by the amounts set out
in Appendix 7-A in respect of each ODP tonne of reductions in production or/and
consumption not achieved in any one year.
10. The Funding components of this Agreement will
not be modified on the basis of any future Executive Committee decision that
may affect the Funding of any other production sector projects or any other
related activities in the Country.
11. The Country will comply with any reasonable
request of the Executive Committee and the Lead IA to facilitate implementation
of this Agreement. In particular, it will provide access by the Lead IA to
information necessary to verify compliance with this Agreement.
12. All of the agreements set out in this
Agreement are undertaken solely within the context of the Montreal Protocol and
as specified in this Agreement. All terms used in this Agreement have the
meaning ascribed to them in the Protocol unless otherwise defined herein.
Appendix 1-A. The Substances
|
Annex
A: |
Group
I |
CFC-11,
CFC-12, CFC-113, CFC-114, CFC-115 |
|
Annex
A |
Group
II |
Halon
1301 |
|
Annex
B |
Group
I |
CFC-13 |
|
Annex
B |
Group
II |
CTC |
Appendix 2-A. The targets, and funding
Table
1: ODS Phase out Targets
|
(ODP tonnes) |
Baseline |
2004 |
2005 |
2006 |
2007 |
2008 |
2009 |
2010 |
|
CFCs 1 |
|
|
|
|
|
|
|
|
|
Montreal Protocol
reduction schedule (production) |
47,004 |
47,004 |
23,502 |
23,502 |
7,050.6 |
7,050.6 |
7,050.6 |
02 |
|
Montreal Protocol
reduction schedule (consumption) |
57,819 |
57,819 |
28,910 |
28,910 |
8,673 |
8,673 |
8,673 |
02 |
|
2. Max allowable CFCs production |
|
25,300 |
18,750 |
13,500 |
7,4003 |
550 |
550 |
02 |
|
3. Max allowable CFCs total consumption |
|
25,300 |
18,750 |
13,500 |
7,400 |
550 |
550 |
02 |
|
4. Max allowable CFC-11 consumption limit in PU
Foam sector |
|
10,500 |
9,000 |
7,000 |
400 |
0 |
|
|
|
5. Max. allowable net CFC exports 4 |
|
NL5 |
NL5 |
4002 |
2002 |
1002 |
502 |
0 |
|
CTC |
|
|
|
|
|
|
|
|
|
Montreal
Protocol reduction schedule (production) |
29,367.4 |
|
4,405 |
4,405 |
4,405 |
4,405 |
4,405 |
0 |
|
Montreal Protocol
reduction schedule (consumption) |
55,903 |
|
8,385 |
8,385 |
8,385 |
8,385 |
8,385 |
0 |
|
6. Max allowable sum of production and imports
of CTC 6 |
|
54,857 |
38,686 |
32,044 |
22,724 |
12,768 |
13,415 |
12,217
7 |
|
7. Max allowable CTC as CFC feedstock |
|
39,306 |
28,446 |
21,276 |
11,396
|
847
8 |
847
8 |
0
9 |
|
Halon |
|
|
|
|
|
|
|
|
|
Montreal Protocol
reduction schedule (production) |
40,993 |
40,993 |
20,497 |
20,497 |
20,497 |
20,497 |
20,497 |
0 |
|
Montreal Protocol
reduction schedule (consumption) |
34,187 |
34,187 |
17,094 |
17,094 |
17,094 |
17,094 |
17,094 |
0 |
|
8. Max allowable halon 1301 production |
|
2000 |
2000 |
1000 |
1000 |
1000 |
1000 |
0 |
|
9. Max allowable halon 1301 consumption and
export 10 |
|
1500 |
1500 |
1000 |
1000 |
1000 |
1000 |
0 |
|
10. Max. allowable net halon 1301
export |
|
NL5 |
NL5 |
200 |
200 |
100 |
100 |
0 |
1.
CFCs include Annex A Group I and Annex B Group I.
2.
Except for essential uses as agreed by the Parties.
3.
Production based on the MP plus 10% allowed for basic domestic needs.
4.
Net exports defined as exports-imports.
5.
Not limited (NL): No limits on export/import of CFCs.
1) Not
including CTC production for non-ODS feedstock.
2) 12,217
equals 11,997 (Row 2) plus 220 (Row 4) in the existing agreement for CTC/PA
phase-out (Phase I).
3) Estimated
CTC production (770 MT) used as CFC production (550 MT CFCs) to meet MDI
consumption. In case of import of MDI quality CFC, the national production of
CFC and CTC will reduce accordingly to ensure that the national consumption for
CFC and CTC stay within the agreed consumption levels.
4) Not
including CTC as CFC feedstock for CFC production for essential use.
5)
For consistency with the
halon 1301 production phase-out, China will limit use of halon 1301 to military
and essential use (to be approved by the Parties) and limit export of halon
1301 to Article 5 countries as given in the table above (include essential
uses).
Table
2: Multilateral Fund Support (in US$ thousands)
|
|
2004 |
2005 |
2006 |
2007 |
2008 |
2009 |
2010 |
||
|
CFC production sector |
|
|
|
|
|
|
|
||
|
1. Total annual funding in the existing
agreement for CFC production phase-out |
13,000 |
13,000 |
13,000 |
13,000 |
13,000 |
13,000 |
- |
||
|
2. Total adjusted annual funding for the APP |
13,000 |
13,000 |
13,000 |
24,000 |
7,500 |
7,500 |
- |
||
|
3. Programme support cost (7.5%) |
975.00 |
975.00 |
975.00 |
1.800 |
562.5 |
562.5 |
- |
||
|
Foam sector |
|
|
|
|
|
|
|
||
|
4. Total annual funding in the existing
agreement for the PU foam sector |
10,903 |
10,903 |
3,320 |
2,676 |
1,767 |
1,767 |
- |
||
|
5. Total adjusted annual funding for the APP |
10,903 |
10,903 |
3,320 |
2,676 |
1,767 |
1,767 |
- |
||
|
6. Programme support cost as per the existing
agreement for the foam sector plan |
961.27 |
961.27 |
282.80 |
240.84 |
159.03 |
159.03 |
- |
||
|
7. Agreed new funding for the APP 1 |
5,000 |
5,000 |
0 |
0 |
0 |
0 |
- |
||
|
8. Agreed programme support cost for the APP
(7.5%) |
375.00 |
375.00 |
0 |
0 |
0 |
0 |
- |
||
|
9. Total agreed
funding |
28,903 |
28,903 |
16,320 |
26,676 |
9,267 |
9,267 |
- |
||
|
10. Total agreed
support cost |
2,311.27 |
2,311.27 |
1,257.80 |
2,040.84 |
721.53 |
721.53 |
- |
||
Note:
This finding request includes only compensation for early phase-out of CFC and
halon 1301, and some capacity building activities. It excludes fund request for
early phase-out of CTC which would be requested separately in the CTC/PA II
sector plan which is under preparation.
Appendix 3-A. Funding approval schedule
Funding
will be considered for approval at the first meeting of the calendar year of
the Annual Implementation Programme.
Appendix 4-A. Format of Annual Implementation Programme
1. Data
|
Country |
|
|
Year
of plan |
|
|
#
of years completed |
|
|
#
of years remaining under the plan |
|
|
Target
CFC/CTC/halon 1301 production of the preceding year |
|
|
Target
CFC/CTC/halon 1301 production of the year of plan |
|
|
Target
CFC-11 consumption of the preceding year in the foam sector |
|
|
Target
CFC-11 consumption of the year of plan in the foam sector |
|
|
Level
of funding requested |
|
|
Lead
implementing agency |
|
2. Targets
|
Indicators |
Preceding year |
Year of plan |
Reduction
|
|
|
Supply
of ODS |
Production
(CFCs/CTC/halon 1301) |
|
|
|
|
Import
(CFCs/CTC) |
|
|
|
|
|
Total
(1) (CFCs/CTC/halon 1301) |
|
|
|
|
|
Demand
of ODS |
Foam
(CFC-11) |
|
|
|
|
CFC
feedstock (CTC) |
|
|
|
|
|
Halon
1301 |
|
|
|
|
|
Total
(2) (CFCs/CTC/halon 1301) |
|
|
|
|
3. Industry
Action
|
Sector |
Production
preceding year (1) |
Production
year of plan (2) |
Reduction
within year of plan (1)-(2) |
Number
of projects completed |
ODS
phase-out (in ODP tonnes) |
|
CFCs |
|
|
|
|
|
|
CTC |
|
|
|
|
|
|
Halon
1301 |
|
|
|
|
|
|
Total |
|
|
|
|
|
|
|
|
|
|
|
|
|
Foam |
|
|
|
|
|
|
Total |
|
|
|
|
|
4. Technical
Assistance
Proposed Activity: _____________________________
Objective: _____________________________
Target Group: _____________________________
Impact: _____________________________
5. Government
Action
|
Policy activity planned |
Schedule of implementation |
|
Policy
control on ODS production, consumption, import and export |
|
|
Public
awareness |
|
|
Others |
|
6. Annual
Budget
|
Activity |
Planned expenditures (US $) |
|
|
|
|
Total |
|
Appendix 5-A. Monitoring Institutions and Roles
1. The Government of China agrees to ensure
accurate monitoring of the ODS phase-out under this Agreement. The ODS
production and consumption figures provided under this Agreement will be
consistent with China’s reports to the Ozone Secretariat under Article 7 of the
Montreal Protocol. The Government of China also agrees to allow independent
verification conducted by the World Bank, and in addition, external evaluation
as may be directed by the Executive Committee, to verify that annual ODS
production levels correspond to those agreed. Verification of CFC-11
consumption in the foam sector will be done according to the existing agreement
for the PU foam sector.
2. Since the implementation of this CFC/Halon
Accelerated Phase out Plan consists of the implementation of originally
independent phase-out plans of (1) CFC production, (2) CFC consumption in the
PU foam sector, and (3) CTC and PA (Phase I), a consolidated reporting of all those
plans (see the table as below) is required. Under this CFC/Halon Accelerated
Phase out Plan, the World Bank as lead agency will facilitate an Executive
Summary each year on implementation status of the APP and all sector plans
active in the year covered by the verification. The list below shows ongoing
sector plans with verification obligations.
|
Sector Plans in China |
Implementing Agency |
|
1. Halon Sector Plan |
World
Bank |
|
2. CFC Production Sector Plan |
World
Bank |
|
3. Foam Sector Plan (CFC-11) |
World
Bank |
|
4. Tobacco Sector Plan (CFC-11) |
UNIDO |
|
5. Solvent Sector Plan (CFC-113, CTC and
TCA) |
UNDP |
|
6. CTC and PA Sector Plan (phase I) (CTC and
CFC-113) |
World
Bank |
|
7. TCA Sector Plan |
World
Bank |
|
8. Refrigeration Servicing Sector Plan (
CFC) |
UNIDO |
|
9. CTC and PA Sector Plan (phase II) (under
preparation) |
World
Bank |
|
10. Pharmaceutical Aerosol Sector Plan (under
preparation) |
World
Bank |
|
11. MDI Sector Plan (preparation to start) |
UNIDO |
3. In addition to monitoring of the
implementation through the responsible agencies as well as the lead agency, the
Project Management Office (PMO) affiliated to the China State Environmental
Protection Administration (SEPA) as well as other state governments will
monitor implementation, being supervised by the China Leading Group of Ozone
Layer Protection.
4. The implementation part of the Executive
Summary Report to be submitted to the Executive Committee will provide an
overall assessment of the ODS production and consumption for the year
concerned, using the definition of the Montreal Protocol on production and
consumption. This should be based on verification results from cooperating
implementing agencies who implement sector plans and should include the
verified import and export data on the relevant controlled substances. The release
of funding under the existing ODS Phase-out Plans will be subject to the
acceptance of the annual implementation programmes of each individual sector
plan as part of the consolidated Executive Summary Report.
Appendix 6-A. Role of the Lead IA
The
Lead IA will be responsible for a range of activities to be specified in the
project document along the lines of the following:
(a) ensuring performance and financial
verification in accordance with this Agreement and with its specific internal
procedures and requirements as set out in the Country’s phase-out plan;
(b) providing verification to the Executive
Committee that the Targets have been met and associated annual activities have
been completed as indicated in the implementation programme
(c) assisting the Country in preparation of the
Implementation Programme;
(d) ensuring that achievements in previous
Implementation Programmes are reflected in future Implementation Programme;
(e) a report on the implementation of the Annual
Implementation Programme of the preceding year using the Montreal Protocol
definition on production and consumption and the Annual Implementation
Programme for the year is to be prepared and submitted to the first meeting of
the Executive Committee in each year;
(f) ensuring that technical reviews undertaken by
the Lead IA are carried out by appropriate independent technical experts;
(g) carrying out required supervision missions;
(h) ensuring the presence of an operating
mechanism to allow effective, transparent implementation of the Implementation
Programme and accurate data reporting;
(i) verification for the Executive Committee that
production of the Substances has been eliminated in accordance with the
Targets;
(j) coordinate the activities of the Cooperating
IAs, if any;
(k) ensuring that disbursements made to the
Country are based on the use of the Indicators; and
(l) providing assistance with policy, management
and technical support when required.
Appendix 7-A Reductions in Funding for Failure to Comply
In
accordance with paragraph 9 of the Agreement, the amount of funding provided
may be reduced according to the penalty stipulations in the existing agreements
for ODS phase out in the CFC production, PU foam, halon and the refrigeration
servicing sectors.
Appendix 8- Existing agreements between China and the
Executive Committee on the phase-out of ODS production and consumption
|
(ODP tonnes) |
Baseline |
2004 |
2005 |
2006 |
2007 |
2008 |
2009 |
2010 |
|
|
CFCs |
|
|
|
|
|
|
|
|
|
|
CFCs Production |
47,004 |
25,300 |
18,750 |
13,500 |
9,600 |
7,400 |
3,200 |
01 |
|
|
Annual
national CFC-11 consumption limit in the agreement for the FSP) |
|
13,100 |
10,400 |
7,700 |
4,130 |
3,800 |
300 |
0 |
|
|
Annual
CFC-11 consumption limit in PU foam sector as per the agreement for the foam
sector plan |
|
11,666 |
9,646 |
7,164 |
3,821 |
3,553 |
102 |
0 |
|
|
CFC-11 consumption
limit as per the agreement for the Tobacco sector |
|
500 |
300 |
150 |
0 |
|
|
|
|
|
CFC-113 consumption
control targets as per the agreement for the solvent sector |
|
|
|
|
03 |
|
|
|
|
|
CFCs consumption limits
in domestic refrigeration sector for manufacturing |
|
|
|
|
03 |
|
|
|
|
|
Max allowable CFC-113
consumption as per the agreement for the PA sector |
17.2 |
14 |
14 |
10.8 |
8.4 |
0 |
|
|
|
|
Max allowable CFCs
consumption in the servicing sector |
|
5,083 |
4,572 |
3,790 |
2,997 |
2,317 |
1,786 |
1,181 |
|
|
CTC |
|
|
|
|
|
|
|
|
|
|
Max allowable sum of
production and net imports as per the agreement for the PA/CTC sector plan
for CTC 4 |
55,903.8 |
54,857 |
38,686 |
32,044 |
26,457 |
23,583 |
17,592 |
11,990 |
|
|
Max allowable
consumption in the 25 PA applications as per the agreement for the PA/CTC
sector plan (phase I) |
3,825 |
5,049 |
493 |
493 |
493 |
493 |
493 |
220 |
|
|
CTC used as feedstock
for CFC production as per the agreement for the PA/CTC sector plan
(phase I) |
N/A |
39,306 |
28,446 |
21,276 |
15,129 |
11,662 |
5,042 |
05 |
|
|
CTC consumption control
targets in solvent sector as per the agreement for the Solvent Sector Plan |
|
02 |
|
|
|
|
|
|
|
|
Halons |
|
|
|
|
|
|
|
|
|
|
Halon 1301 production |
|
6,000 |
6,000 |
1,500 |
1,500 |
1,500 |
1,500 |
0 |
|
|
Halon 1301 consumption |
1,500 |
1,500 |
1,000 |
1,000 |
1,000 |
1,000 |
0 |
||
|
Halon 1211 production |
5,970 |
5,970 |
0 |
|
|
|
|
||
|
Halon 1211 consumption |
5,670 |
5,670 |
0 |
|
|
|
|
Note:
1. Save for any CFC production that may be agreed
by the Parties to meet essential uses for China.
2. Save for any CFC-113 consumption or CTC solvent
consumption that may be agreed by the Parties to be essential for China after
2010.
3. Not including CFC consumption in servicing
sector.
4. Including CTC production for CFC production and
ODS feedstock applications but does not include CTC production for non-ODS
feedstock..
5. Excluding CTC as CFC feedstock for CFC
production for essential uses.
Appendix 9-A. Enforcement and penalties related to illegal
production, trade and export in CFCs and halons
|
Year of effectiveness |
Actions |
|
January
2005 |
1. China
will continue on-site monitoring of the production of CFC until 2010 as
currently implemented under the CFC production sector plan. 2. China
will strengthen monitoring of the halon 1301 production and sales by
quarterly on site review of production and sales records until 2010. |
|
December
2008 |
1. Issuance
of a new regulation by the State Council, for a penalty system which
constitutes a significant penalty, e.g. confiscation of any sales value in
any illegal ODS production activity and a penalty several times of its sales
value. |
|
December
2009 |
1. Update the Air Pollution Prevention and
Control Law with the same level of financial penalties as in the regulatory
system mentioned above with addition of prison terms for illegal ODS related
activities. |
(UNEP/OzL.Pro/ExCom/44/73, Decision
44/59, para. 247 (a,
b)).
(Supporting document: UNEP/OzL.Pro/ExCom/44/73 Annex XVII).