1. The
Executive Committee approves in principle a total of US $9 million in
funding for the phased reduction and complete phase-out of consumption of
CFC-11, CFC-12 and CFC-115 in Turkey by 2006. This level of funding takes into
account the significant acceleration of the agreed phase-out in Turkey and the
resulting reduction in ODS emissions. This is the total funding that will be
available to Turkey from the Multilateral Fund for the total elimination of CFC
use in the refrigeration sector in Turkey as well as for all other sectors
using these substances, (e.g., foams, aerosols, solvents, etc.). The agreed
level of funding will be paid out in installments in the exact amount of US
dollars specified in paragraph 2, and on the basis of the understanding set out
in this agreement.
2. By
this agreement, Turkey commits that in exchange for the funding specified
below, it will eliminate its total CFC consumption in accordance with the
individual and aggregate consumption targets as indicated in Table 1 below.
Table 1. National control
targets for CFC-11, CFC-12 and CFC-115 consumption in ODP tonnes
|
|
1999 Baseline |
2001 |
2002 |
2003 |
2004 |
2005 |
2006 |
2007 |
2008 |
2009 |
|
Maximum allowable CFC-12 consumption (ODP
tonnes) |
736 |
700 |
650 |
334 |
166 |
100 |
0 |
0 |
0 |
0 |
|
Maximum allowable CFC-11 consumption (ODP
tonnes) |
1,049 |
300 |
250 |
200 |
150 |
50 |
0 |
0 |
0 |
0 |
|
Maximum allowable CFC-115 consumption (ODP
tonnes) |
9 |
9 |
9 |
0 |
0 |
0 |
0 |
0 |
0 |
0 |
|
Maximum allowable total ODP (ODP tonnes) |
|
977 |
909 |
534 |
316 |
150 |
0 |
0 |
0 |
0 |
|
Total agreed funding (US$ million) |
|
3.5 |
2.5 |
1 |
0.75 |
0.75 |
0.5 |
0 |
0 |
0 |
|
Agency support cost (US$ million) |
|
0.295 |
0.175 |
0.150 |
0.045 |
0.03 |
0.03 |
0.03 |
0.03 |
0.025 |
3. The
Executive Committee also agrees in principle that the funds will be provided at
the last meeting of the Executive Committee in a given year, for the exact
amount listed in the above table for that year and on the basis of an annual
implementation plan for the following year, subject to the performance
requirements contained in this agreement. Thus, for example, the payment
indicated in year 2001 will be for activities to be undertaken in 2002, and so
on.
4. Payments
noted in Table 1, other than those for 2001, will be released based on
confirmation that: the agreed phase-out targets noted in Table 1 for the
previous year have been achieved; it has been verified that the activities
planned for the previous year were undertaken in accordance with the annual
implementation plan, and CFC phase-out contracts have been signed amounting to
at least 80 per cent of the Multilateral Fund funding approved for the relevant
annual programme. For example, payment in 2002 for the implementation of the
2003 work programme will be conditional on satisfactory verification that
Turkey has, as a minimum, met its consumption targets for 2001 as specified in
Table 1 and as provided in detail in the 2002 implementation plan. Payment in
2003 for the 2004 implementation plan will be released based on confirmation
that the 2002 consumption targets have been met, all 2002 implementation plan
activities have been completed and contracts amounting to at least 80 per cent
of the 2002 Multilateral Fund grant have been signed; and so on for future
years. In the event that contracts totaling 80 per cent of the Multilateral
Fund funding available for a given year have not been signed, funding
equivalent to the deficit will be held back and considered for release by the
Executive Committee when all additional contracts have been signed and the
targets met.
5. The
Government of Turkey agrees to ensure accurate monitoring of the phase-out. The
Government of Turkey will provide regular reports, as required by its
obligations under the Montreal Protocol and this Agreement. Consumption figures
provided under this agreement will be consistent with Turkey’s reports to the
Ozone Secretariat under Article 7 of the Montreal Protocol.
6. The
Government of Turkey also agrees to allow independent verification audits as
provided for in this agreement, and in addition, external evaluation as may be
directed by the Executive Committee, to verify that annual CFC consumption
levels correspond to those agreed in Table 1 and that implementation of the
sector plan proceeds as scheduled and agreed in annual implementation
programmes.
7. The
Turkish refrigeration plan which supports this Agreement, Turkish Country
Programme and other related documentation may include estimates of specific
funds that were thought to be needed for specific items. Notwithstanding this,
the Executive Committee wishes to provide Turkey with maximum flexibility in
using the agreed funds to meet the consumption limits agreed in Table 1. The
Executive Committee understands that during implementation, the funds provided
to Turkey pursuant to this Agreement may be used in any manner consistent with
this Agreement that Turkey believes will achieve the smoothest possible CFC
phase-out in the refrigeration sector, consistent with operational procedures
as agreed between Turkey and the World Bank in the refrigeration sector plan as
revised and as indicated in the annual implementation programmes. In the
Executive Committee’s acknowledgement of the flexibility available to Turkey to
achieve a complete CFC refrigeration sector phase-out, it is noted that Turkey
is committing to contribute the level of resources necessary to implement the
plan and to achieve the consumption limits in paragraph 2 of this agreement.
8. The
Government of Turkey agrees that the funds being agreed in principle by the
Executive Committee at its 35th Meeting for the complete phase-out of CFC-11,
CFC-12 and CFC-115 consumption are the total funding that will be available to
Turkey to allow its full compliance with the reduction and phase-out as agreed
with the Executive Committee of the Multilateral Fund, and that no additional
Multilateral Fund resources will be forthcoming for any related activities in
the refrigeration sector. It is also understood that aside from the agency fee
referred to in paragraph 10 below, the Government of Turkey, the Multilateral
Fund, and its Implementing Agencies, and bilateral donors will neither request
nor provide further Multilateral Fund-related funding for the accomplishment of
the total phase-out of CFCs in the refrigeration sector.
9. The
Government of Turkey agrees that if the Executive Committee meets its
obligations under this Agreement, but Turkey does not meet the reduction
requirements outlined in paragraph 2, or other requirements outlined in this
document, the Implementing Agency and the Multilateral Fund will withhold
funding for subsequent tranches of funding outlined in paragraph 2 until such
time as the required reduction has been met. It is clearly understood that the
fulfillment of this agreement depends on satisfactory performance by both the
Government of Turkey and the Executive Committee of their obligations. In
addition, Turkey understands that with respect to all calendar year targets
beginning with 2002, as set out in paragraph 2 of this agreement, the
Multilateral Fund will reduce the subsequent tranche and therefore the total
funding for CFC-11, CFC-12 and CFC-115 phase-out on the basis of
US $15,000 per ODP tonne of reduction not achieved in any year.
10. The
World Bank has agreed to be the Implementing Agency for the implementation of
this sector plan which will be completed in 2006. It is also agreed that
monitoring will continue until 2009 in order to ensure compliance during the
period 2006 to 2009. A fee of 9 per cent of the sector plan annual funding has
been agreed in accordance with the provisions of this Agreement, and
distributed as shown in Table 1. As the Implementing Agency, the World Bank
will be responsible for the following:
(a) ensuring performance and financial verification
in accordance with specific World Bank procedures and requirements as specified
in the Turkish refrigeration sector plan, as revised;
(b) reporting on the implementation of the annual
implementation programmes to be included as part of each annual programme
starting with the submission for the 2003 annual implementation programme
prepared in 2002;
(c) providing verification to the Executive
Committee that the control targets listed in Table 1 and the associated
activities have been met;
(d) ensuring that technical reviews undertaken by
the World Bank are carried out by appropriate independent technical experts;
(e) assisting Turkey in preparation of annual
implementation programmes, which will incorporate achievements in previous
annual programmes;
(f) carrying out required supervision missions;
(g) ensuring the presence of an operating
mechanism to allow effective, transparent implementation of the programme, and
accurate data reporting;
(h) verification for the Executive Committee that
CFC consumption for the refrigeration sector has been completed based on the
schedules listed in Table 1;
(i) ensuring that disbursements are made to
Turkey based on agreed performance targets in the project and provisions in
this Agreement;
(j) providing policy development assistance when
required.
9. The
funding components of this Decision shall not be modified on the basis of
future Executive Committee decisions that may affect the funding of any other
consumption sector projects or any other related activities in the country.
(UNEP/OzL.Pro/ExCom/35/67, Decision 35/55, para. 91).
(Supporting document:
UNEP/OzL.Pro/ExCom/35/54, 35/54/Corr.1 and 35/54/Add.1).