Criteria and rating scheme for overall assessment


(from Section II of Project Completion Report)

Part A: Assessment of Quantitative Project Performance Data 

Category 

Criteria 

Range 

Rating 

Pre-conditions for Completion* 

ODS phase-out as approved 

0 or 20 

 

Conversion completed (no more CFC in use, ODS-free production has started) 

0 or 20 

 

Certified equipment destruction 

0 or 20 

 

Delays 

On time 

15 

 

6 to 12 months delay 

0 

More than 12 months delay 

-15 

Cost-effectiveness of MLF Funding 

Better than approved by 5% or more 

5 

 

As approved, or better by up to 5% 

0 

Less cost-effective than approved 

-5 

Subtotal A 

   

 

Part B: Qualitative Rating of Project Performance** 

Project Preparation 

Quality of project design 

5, 3 or 1 

 

Technology Choice 

Conversion technology 

5, 3 or 1 

 

Type of equipment 

5, 3 or 1 

 

Supplier 

5, 3 or 1 

 

Management of Risks 

Safety / health protection 

5, 3 or 1 

 

Maintenance of equipment 

5, 3 or 1 

 

Maintaining product quality 

5, 3 or 1 

 

Preventing return to ODS use 

5, 3 or 1 

 

Subtotal B 

   

 

Total Score 

Highly satisfactory

Satisfactory

Less satisfactory 

100 to 120

75 to 99

48 to 74 

 

* The overall rating will be calculated only if the pre-conditions for completion, as defined by the Executive Committee in Decision 28/2, are met and documented (applicable for projects completed after July 1999).

** Please rate the project performance with regard to quality/appropriateness using the following scale for each category: Highly satisfactory: (5); Satisfactory: (3); Less satisfactory: (1).

(UNEP/OzL.Pro/ExCom/32/44, Decision 32/18, para 29).

(Supporting document: UNEP/OzL.Pro/ExCom/32/19, Corr.1 and Add.1).