Schedule for submission of outstanding project completion reports (PCRs) in 2001*


UNDP  

Schedule 

Sector 

Investment PCRs 

Non-Investment PCRs 

31 Mar 01  

UNDP will concentrate on foam PCRs until 15th February 2001, and will deliver the outstanding solvent PCRs until 31st January 2001 and the three aerosol PCRs and one halon PCR by end-February 2001. After that, the remaining PCRs would be primarily in the foam and refrigeration sectors. 

30 

10 

30 Jun 01 

30 

10 

30 Sept 01 

30 

10 

31 Dec 01 

29 

10 

 

 
 

Total 

 

119 

40 

UNEP  

Schedule 

Sector 

Investment PCRs 

Non-Investment PCRs 

31 Jan 01 

TAS 

 

20 

31 Jan 01 

Training 

 

 

Total 

   

22 

UNIDO  

Schedule 

Sector 

Investment PCRs 

Non-Investment PCRs 

31 Jan 01 

Foam 

 

31 Mar 01 

Aerosol** 

 

31 Mar 01 

Refrigeration 

22 

 

31 Jul 01 

Refrigeration 

 
 

Total 

 

33 

 

IBRD  

Schedule 

Sector 

Investment PCRs 

Non-Investment PCRs 

31 Jan 01 

Foam (13)***

Solvent (2)

Compressor (3) 

18 

 

31 Feb 01 

Halon (0)

Refrigeration (5)

All Sectors (5) 

10 

 

31 Mar 01 

All Sectors 

10 

 

31 Apr 01 

Aerosol (3)

All Sectors (10) 

13 

 

31 May 01 

All Sectors 

 

31 Jun 01 

TAS (2) INS (2) 

 

31 Jul 01 

Foam (1) All Sectors (7) TAS (1) 

Total 

 

67 

*The table shows expected PCRs for projects completed as of 31 December 1999 and takes into account the number of outstanding PCRs as of 31 October 2000. The Implementing Agencies will, in addition to the above schedule, submit PCRs in 2001 for projects completed through 2000 and up to June 30, 2001.

**The completion reports on 2 other aerosol projects in Kenya are pending until warehouse issues are cleared.

***Some of these foam projects will have PCRs ready for submission before January 2000.

(UNEP/OzL.Pro/ExCom/32/44, Decision 32/18, para 29).

(Supporting document: UNEP/OzL.Pro/ExCom/32/19, Corr.1 and Add.1).