
Business
plans for the years 2004-2006 of UNEP, UNDP,
UNIDO and the World Bank
The Forty-second Meeting of the Executive Committee
decided:
(a) to endorse the 2004-2006 business
plan of UNDP, as contained in documents UNEP/OzL.Pro/ExCom/42/8
and Corr.1 and as orally amended to include a possible project for Cuba, while
noting that endorsement did not denote approval of the projects identified
therein nor their funding levels; and
(b) to approve the following performance
indicators for UNDP:
|
Category
|
Item
|
Weighting
|
2004 target
|
|
Approval
|
Number of annual programmes of multi-year agreements
approved vs. those planned
|
20
|
21
|
|
Approval
|
Number of individual projects/activities (investment
projects, RMPs, halon banks, TAS) approved vs. those planned
|
20
|
32
|
|
Implementation
|
Milestone activities completed (e.g. policy measures,
regulatory assistance)/ODS levels achieved
for approved multi-year annual tranches vs. those planned
|
20
|
12
|
|
Implementation
|
ODS phased-out for individual projects
vs. those planned per progress reports
|
5
|
4,919 ODP
tonnes
|
|
Implementation
|
Project completion (pursuant to Decision 28/2 for investment projects) and as defined for non-investment
projects vs. those planned in progress reports
|
5
|
113
|
|
Implementation
|
Percentage of policy/regulatory
assistance completed vs. that planned
|
10
|
N/a
|
|
Administrative
|
Speed of financial completion vs. that required per
progress report completion dates
|
10
|
217
|
|
Administrative
|
Timely submission of project completion reports vs.
those agreed
|
5
|
Yes
|
|
Administrative
|
Timely submission of progress reports and responses
unless otherwise agreed
|
5
|
On 1 May 2004
|
(UNEP/OzL.Pro/ExCom/42/54,
Decision 42/8, para. 50).
(Supporting document: UNEP/OzL.Pro/ExCom42/54, Annex II).
The Forty-second Meeting of the Executive Committee
decided:
(a) to endorse the 2004-2006 business
plan of UNEP as contained in document UNEP/OzL.Pro/ExCom/42/9 and
as orally amended to include the projects already submitted for Bangladesh and
a non-governmental organization methyl bromide project, while noting that endorsement did not denote approval
of the projects identified therein nor their funding levels; and
(b) to approve the following performance
indicators for UNEP:
|
Category
|
Item
|
Weighting
|
2004 target
|
|
Approval
|
Number of annual programmes of multi-year agreements
approved vs. those planned, may not be applicable to UNEP
|
20
|
Not
applicable to UNEP
|
|
Approval
|
Number of individual projects/activities (investment
projects, RMPs, halon banks, TAS) approved vs. those planned
|
20
|
28
countries (i.e. 100%). UNEP believes that a realistic
achievement is 17 countries (i.e. 60%).
|
|
Implementation
|
Milestone activities completed (e.g. policy measures,
regulatory assistance)/ODS levels achieved
for approved multi-year annual tranches vs. those planned, may not be
applicable to UNEP
|
20
|
Not
applicable to UNEP
|
|
Implementation
|
ODS phased-out for individual projects
vs. those planned per progress reports, may not be applicable to UNEP
|
5
|
21.2
ODP tonnes from the IS project for Algeria (i.e. 100%)
|
|
Implementation
|
Project completion (pursuant to Decision 28/2 for investment projects) and as defined for non-investment
projects vs. those planned in progress reports
|
5
|
38
projects (i.e. 100%)
|
|
Implementation
|
Percentage of policy/regulatory
assistance completed vs. that planned
|
10
|
11
projects (i.e. 100%). UNEP believes that a realistic achievement
is 9 projects (i.e. 80%)
|
|
Administrative
|
Speed of financial completion vs. that required per
progress report completion dates
|
10
|
100%
|
|
Administrative
|
Timely submission of project completion reports vs.
those agreed
|
5
|
Timely
submission
|
|
Administrative
|
Timely submission of progress reports and responses
unless otherwise agreed
|
5
|
Timely
submission
|
(UNEP/OzL.Pro/ExCom/42/54,
Decision 42/9, para. 52).
(Supporting document: UNEP/OzL.Pro/ExCom42/54, Annex III).
The Forty-second Meeting of the Executive Committee
decided:
(a) to endorse the 2004-2006 business
plan of UNIDO, as contained in documents UNEP/OzL.Pro/ExCom/42/10
and Corrs.1 and 2 and as orally amended, to bring forward the Serbia and
Montenegro project from 2005, modify the phase-out in the
MDI and RMP projects in China and remove the methyl
bromide project in Viet Nam, taking into account
the clarification provided by the representative of UNIDO, while noting that
endorsement did not denote approval of the projects identified therein nor
their funding levels; and
(b) to approve the following performance
indicators for UNIDO:
|
Category
|
Item
|
Weighting
|
2004 target
|
|
Approval
|
Number of annual programmes of multi-year agreements
approved vs. those planned, may not be applicable to UNEP
|
20
|
16 approved + 14 new ones
|
|
Approval
|
Number of individual projects/activities (investment
projects, RMPs, halon banks, TAS) approved vs. those planned
|
20
|
7
|
|
Implementation
|
Milestone activities completed (e.g. policy measures,
regulatory assistance)/ODS levels achieved
for approved multi-year annual tranches vs. those planned
|
20
|
16
|
|
Implementation
|
ODS phased-out for individual projects
vs. those planned per progress reports
|
5
|
5,666 ODP tonnes
|
|
Implementation
|
Project completion (pursuant to Decision 28/2 for investment projects) and as defined for non-investment
projects vs. those planned in progress reports
|
5
|
70
|
|
Implementation
|
Policy/regulatory assistance
completed vs. that planned
|
10
|
4
|
|
Administrative
|
Speed of financial completion vs. that required per
progress report completion dates
|
10
|
12 months
|
|
Administrative
|
Timely submission of project completion reports vs.
those agreed
|
5
|
On time
|
|
Administrative
|
Timely submission of progress reports and responses
unless otherwise agreed
|
5
|
On time
|
(UNEP/OzL.Pro/ExCom/42/54,
Decision 42/10, para. 54).
(Supporting document: UNEP/OzL.Pro/ExCom42/54, Annex IV).
The Forty-second
Meeting of the Executive Committee decided:
(a) to endorse the 2004–2006 business
plan of the World Bank, as contained in documents UNEP/OzL.Pro/ExCom/42/11
and Corrs. 1 and 2, with the withdrawal of planned chiller
projects in Argentina and Mexico, whose implementation by the World Bank would
be subsumed into those countries’ national implementation plans, as well as the
withdrawal of the accelerated CTC production
phase-out project in China, while noting that endorsement
did not denote approval of the projects identified therein nor their funding
levels; and
(b) to approve the following performance
indicators for the World Bank:
|
Category
|
Item
|
Weighting
|
2004 target
|
|
Approval
|
Number of annual programmes of multi-year agreements
approved vs. those planned, may not be applicable to UNEP
|
20
|
13/13(*)
|
|
Approval
|
Number of individual projects/activities (investment
projects, RMPs, halon banks, TAS) approved vs. those planned
|
20
|
10/10
|
|
Implementation
|
Milestone activities completed (e.g. policy measures,
regulatory assistance)/ODS levels achieved
for approved multi-year annual tranches vs. those planned, may not be
applicable to UNEP
|
20
|
15/15
|
|
Implementation
|
ODS phased-out for individual projects
vs. those planned per progress reports, may not be applicable to UNEP
|
5
|
8,076 ODP
tonnes
|
|
Implementation
|
Project completion
(pursuant to Decision 28/2 for investment projects)
and as defined for non-investment projects vs. those planned in progress
reports
|
5
|
72
|
|
Implementation
|
Percentage of policy/regulatory
assistance completed vs. that planned
|
10
|
N/A
|
|
Administrative
|
Speed of financial completion vs. that required per
progress report completion dates
|
10
|
3 months
|
|
Administrative
|
Timely submission of project completion reports vs.
those agreed
|
5
|
100%
|
|
Administrative
|
Timely submission of progress reports/responses unless
otherwise agreed
|
5
|
100%
|
(UNEP/OzL.Pro/ExCom/42/54,
Decision 42/11, para. 56).
(Supporting document: UNEP/OzL.Pro/ExCom42/54, Annex V).
The Forty-third Meeting of the Executive Committee decided:
(a) to note the report on the status of the 2004
business plans as contained in documents UNEP/OzL.Pro/ExCom/43/5
and Add.1, and the fact that US $94 million remained to be submitted for 22 new
multi-year agreements and 176 other projects contained in the 2004 business
plans;
(b) to urge bilateral and Implementing
Agencies with projects in the 2004 business plans for
countries at risk of non-compliance to submit those
projects to the 44th Meeting as a matter of urgency, and to consider the
projects identified in Table 3 of UNEP/OzL.Pro/ExCom/43/5 as
priority projects; and
(c) to request the Secretariat:
(i) to
send a letter, in conjunction with the Implementing Agencies responsible for
institutional strengthening and the Ozone
Secretariat, to countries at risk of non-compliance
urging them to put forward projects through the implementing and bilateral
agencies as soon as possible;
(ii) to
prepare a document, to be submitted to the 44th Meeting of the Executive
Committee, on a potential procedure for intersessional
approval of projects for countries at risk of non-compliance,
when such projects were in the business plan for a given year
and there was no disagreement between the Secretariat and
the implementing agency; and
(iii) to
include in the document to be submitted to the 44th Meeting of the Executive
Committee an examination of the reasons for the non submission of projects for
countries at risk of non compliance.
(UNEP/OzL.Pro/ExCom/43/61, Decision 43/3, para. 33).
